PROJECT

Projects

Environmental & Social Review Summary

Project Number

44364

Company Name

SHAMOL ZARAFSHAN ENERGY FE LLC

Date ESRS Disclosed

Mar 4, 2022

Country

Uzbekistan

Region

Central Asia and Turkiye

Last Updated Date

Nov 12, 2022

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Jul 21, 2022
Signed : Sep 2, 2022
Invested : Nov 9, 2022

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The IFC is considering a loan to support the Zarafshan Wind Project (the Project), a 500MW (installed capacity) wind IPP project in the Navoi region of Uzbekistan, that is being developed on a bilateral basis between the Government of Uzbekistan (GoU) and Abu Dhabi Future Energy Company PJSC (Masdar or the Company) (https://masdar.ae/). Masdar is a renewable energy and sustainable urban development company wholly owned by Mubadala Investment Company PJSC (Mubadala). The project consists of the construction, operation, and maintenance of the wind farm, which it is anticipated to be operational for 25 years.

 

The proposed project is planned to comprise up to 111 wind turbine generators (WTGs), each with a capacity of up to 4.5 MW. The company is evaluating its turbine vendor options, with the current candidate WTG being the Goldwind 155-4500 model with a hub height of 95 m and a rotor diameter of 155 m. In the event that an alternate turbine is chosen, project impacts will be reassessed, and the ESIA will be revised accordingly and re-disclosed. The wind turbines will be connected to the national grid via a substation located within the project area and two short 220 kV over head transmission lines (OHLs) (approximately 510 m and 630m in length). Additional infrastructure will include a fenced compound area, a site access road, tracks to access each turbine, underground cabling from the turbines to the substation. During project construction, a concrete batching plant will be developed by a local concrete company, at an offsite location to service the project.  This has been deemed to be an associated facility to the project. It is expected that construction will occur from 2022 to late 2024 and, once operational, will supply power to the national grid.

 

The project area is in the Tamdy District of the Navoi region. It lies within the central part of the Kyzylkum Desert and occupies approximately 9,600 hectares, of which construction activities will impact around 150 ha. Portions of the project area are leased to farmers who currently use the land for rough grazing. The project is located approximately 7 km east of the center of Zarafshan City. All land is owned by the government and managed by a government entity referred to as the 'New Committee', on behalf of the central government. The landscape is semi-arid and relatively sparsely populated, with nine villages located in the general vicinity of the project but none within the project area. As a result, the project footprint avoids any need for physical displacement and minimizes risks from shadow flicker or operational noise-related nuisance to local community members. To the north (around 3.5 km distance) is Mount Aktau Important Bird and Biodiversity Area (IBA), which supports breeding and resident populations of raptors that are of international and national conservation status.

 

The project is to be developed under a turnkey EPC Engineering, Procurement and Construction (EPC) contract, executed by Chinese EPC firm SEPCOIII. SEPCOIII will also perform the role of Operations and Maintenance (O&M) contractor for the first two years of operations, after which Masdar Specialized Technical Services will be appointed. It is anticipated that the turbine supplier will perform long Term Service Agreement (LTSA) for the WTG maintenance.

Overview of IFC's Scope of Review

IFC's appraisal of this proposed investment consisted of a review of available environmental, health, safety, and social (EHS) documents, as well as the company's responses to a series of EHS questionnaires. Documentation reviewed included: a Preliminary and Final Environmental and Social Impact Assessment (ESIA), Environmental and Social Monitoring and Management Plan (ESMMP), Stakeholder Engagement Plan (SEP) including the project grievance mechanism, Livelihood Restoration Plan (LRP), and Critical Habit Assessment (CHA), all of which were developed by Wood Group, and the project's existing EHS policies, procedures, and management plans.

Given current travel restrictions related to the COVID19 pandemic, the appraisal included discussions with Masdar project management and corporate representatives responsible for EHS, human resources, and supply chain via video conferencing. The video conferencing occurred in August 2021 and February 2022 and addressed EHS aspects of the project. Discussions were also held with Masdar's EPC contractor, SEPCOIII, and WTG vendor Goldwind in September & October 2021. Identiflight, a vendor of camera-based, technology-led shutdown on-demand equipment to be installed on the project, was consulted in January 2022. 

Further, IFC (jointly with EBRD and ADB) assigned an independent environmental and social consultant (IESC) to conduct an E&S Due Diligence (ESDD) of the project. The ESDD included a 2-day physical site visit completed by the consultants’ local partners in July 2021, attendance of seven public consultation meetings held by the company's ESIA consultant in August 20201, attendance of LRP related disclosure and consultation activities in February 2022, and technical review of project ESIA and associated deliverables. Furthermore, an ornithological-focused site visit was conducted in December 2021. In January 2022, an international consultant was engaged at the request of the Lenders to conduct a labor audit of the selected turbine manufacturing company's facility in Gansu, China.

Contextual risk screening was conducted, including utilizing a gender risk assessment tool to screen the project for gender-related risks (refer to the Performance Standard 4 section below for more detail) and a high-level contextual risk screening conducted at the country level. Contextual risks identified that could be pertinent to this type of project and location included water stress/shortages, labor and working conditions-related risks related to supply chain, forced labor, and gender inequality.

As Masdar is an existing IFC client, IFC's appraisal also considered their EHS performance on existing investments under supervision (links to project disclosures below). Masdar's environmental and social (E&S) performance has been satisfactory. All projects are currently under supervision. Existing Masdar projects in IFC portfolio:

-          https://disclosures.ifc.org/project-detail/ESRS/42525/navoi-scaling-solar

-          https://disclosures.ifc.org/project-detail/ESRS/39339/masdar-jordan

-          https://disclosures.ifc.org/project-detail/ESRS/33839/dolovo-wind

-          https://disclosures.ifc.org/project-detail/ESRS/31627/tafila-wind

                                                  

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ESIA Appendix 6-2 CHA.pdf
Volume 1 Zarafshan Wind Farm Final ESIA B9.pdf
Volume 2 Zarafshan Wind Farm ESIA Figures.pdf
Zarafshan Wind Farm ESIA NTS.pdf
Zarafshan Wind Farm ESMMP_B4.pdf
Zarafshan Wind Farm LRP.pdf
Zarafshan Wind Farm SEP_B7 with Appendices.pdf
Appendix 6-2 CHA_final.pdf