PROJECT

Projects

Environmental & Social Review Summary

Project Number

48387

Company Name

Wind Power GSI Volyn LLC

Date ESRS Disclosed

Nov 6, 2024

Country

Ukraine

Region

Europe

Last Updated Date

Sep 7, 2025

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Dec 17, 2024
Signed : Dec 20, 2024
Invested : Sep 2, 2025

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

IFC is considering a loan to support the Volyn Wind Project, a 147 MW (installed capacity) wind power project (WPP) within the Volyn region of Ukraine (the Project). The project is to be developed by Wind Power GSA Volyn LLC and Wind Power GSA Volyn 3 LLC (collectively known as “the Borrower”), two special purpose vehicles (SPVs) established by GNG Retail Limited, a Cyprus-based holding company for Concern Galnaftogaz JSC (“GNG” or “the Sponsor”), an independent Ukrainian fuel distribution company operating a network of filling stations under the “OKKO” brand (https://www.okko-group.com.ua/en/). The project consists of the development, construction, operation, and maintenance of the wind farm, which is anticipated to be operational for 25 years.

 

The project will involve the installation of 25 Nordex N163/5.X wind turbine generators (WTGs), each with a capacity of up to 6 MW. Each turbine will have a hub height of 120 m and a rotor diameter of 163 m. The wind turbines will be connected to the national grid via a substation within the project area and an 8.7 km 110 kV transmission line (8.154 km via overhead line (OHL), 546 m underground). The project will be served by a network of existing agricultural roads and newly built access roads, along which underground cable lines will be installed. During project construction, an off-site concrete batching plant, to be operated by the borrower’s main contractor, will be installed to service the project. The borrower commenced initial construction activities in July 2024, including road upgrades and earthworks, cabling, and piling works, with project completion expected in Q3 2026.

 

Land required for the project is either owned by the borrower or secured for 29, 45, 47, or 49 years via voluntary lease or easement agreements concluded with public and private landowners. Land within the project area is currently used for crop agriculture. The project’s construction activities will temporarily affect approximately 61.5 ha, while permanent facilities will occupy 45 ha. The 25 turbines will permanently affect an area of 22.6 ha. The pylons of the overhead transmission line (OHL) will affect a total area of 0.13 ha leased from private owners or the village council.

 

The project is situated in the Central European mixed forests ecoregion of the temperate broadleaf and mixed forests biome (as designated by the Worldwide Fund for Nature, WWF). The wind farm site, and its associated OHL are located in a heavily human-modified landscape, dominated by crop agriculture. All project infrastructure is sited within Modified Habitat, per IFC definition. Neither the wind farm nor its associated OHL overlap with Key Biodiversity Areas (KBA) or Legally Protected Areas (LPA).

The project will be developed and operated under a multi-contract scheme executed by international and Ukrainian contractors. An owner’s engineer will be appointed to provide construction supervision services, including E&S monitoring. An independent environmental and social consultant (IESC) has been engaged on behalf of the project Lenders to monitor project development during the construction and initial operational phase.                                                

Overview of IFC's Scope of Review

IFC's appraisal of this proposed investment consisted of a review of available environmental, health, safety, and social documents and the borrower’s responses to a series of E&S questionnaires. Documentation reviewed included an Environmental and Social Impact Assessment (ESIA), a Stakeholder Engagement Plan (SEP), an Environmental and Social Management Plan (ESMP), and a series of E&S sub-plans (developed by a Ukrainian E&S consultancy), and GNG’s E&S policies.

 

The appraisal included discussions with the borrower’s representatives responsible for E&S, project delivery, and their ESIA consultant via video conferencing in July - September 2024. Further, IFC (jointly with EBRD) assigned an independent IESC to conduct an E&S Due Diligence (ESDD) of the project. The ESDD included a 2-day physical site visit completed by the consultants’ local partners in July 2024 and a technical review of project ESIA and associated deliverables. Additionally, IFC undertook a physical site visit in October 2024.

 

GNG is an existing IFC client. IFC's appraisal also considered GNG’s environmental and social performance in its existing investments under supervision (links to project disclosures below). The sponsor's E&S performance has been satisfactory. Existing projects in IFC portfolio include:

-          https://disclosures.ifc.org/project-detail/ESRS/43225/gng-fuels-and-fertilizers

-          https://disclosures.ifc.org/project-detail/ESRS/31723/jv-east

Due to Russia’s invasion of Ukraine, IFC faced limitations in undertaking its environmental and social due diligence for the project.  It may also take longer for the borrower operations to align with the Performance Standards than in other contexts. After constraints related to the invasion are removed, IFC will carry out supplemental field activities and site visits to supplement its due diligence and, as needed, provide support to the borrower toward alignment of the project with IFC Performance Standards.

                                                 

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan