PROJECT

Projects

Environmental & Social Review Summary

Project Number

25924

Company Name

Lydian Resources Company Ltd

Date ESRS Disclosed

May 22, 2007

Country

Kosovo

Region

Europe

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jul 3, 2007
Signed : Jul 27, 2007
Invested : Aug 3, 2007

Sector

Zinc

Industry

Metals and Mining

Department

Gbl Infrastructure & Natural Resources

Project Description

Lydian Resource Company (Lydian or the company) currently holds licenses for three exploration properties in Kosovo and, as part of an exploration joint venture with Newmont Mining Corporation, Lydian also shares ownership of two early stage gold exploration projects in Armenia and Turkey. The project is the continued exploration of these properties, including feasibility studies, environmental and social impact assessments and other preparatory activities.

Overview of IFC's Scope of Review

IFC’s E&S due diligence for the proposed equity investment in Lydian Resource Company (Lydian or the company) has been conducted at both corporate level and project level. A team of environmental and social specialists undertook a week’s appraisal of the projects in Kosovo, including visits to the Draznja, Crepulja and Rahovac prospects and interacted with the company’s consultants and management team on the project details, development plan, the environmental and social impact assessments, consultation conducted to-date, and any updates required thereafter. Additional visits took place in Turkey at the Muratdag property and in Armenia at Armulsar.

The appraisal team reviewed the technical, environmental and social documentation available for each of the exploration properties. The focus was on the preliminary environmental and social data, the need for documenting legal requirements as well as the initial results of exploration works such as trench, drilling and adits. Most of this information has been prepared in 2006 and early 2007. IFC did a detailed review of key strategic documents and corporate policies. During appraisal the IFC team highlighted challenges to come on community relations going forward as the projects progress through exploration works and potential subsequent development. Lydian’s Health, Safety, Environment, Community and Labor (HSEC/L) management, organization and systems for the Draznja project in Kosovo were discussed extensively as it is the most advanced project. These discussions included staffing requirements for Lydian’s HSEC/L functions, and the development of adequate environmental, safety and social management capacity at the corporate level in the medium term when mine development occurs. Information and other documents related to management of environmental, social and labor issues at Armulsar and Muratdag were also discussed.

Discussions were also held with Lydian’s senior corporate executives in the UK, and the exploration and development teams in Pristina, Izmir and Yerevan. In Kosovo, the IFC appraisal team met with representatives of the Podujevo local assembly, the Pristina civil society, local workers, and inhabitants living near Draznja, Crepulja and Rahovac. Formal meetings with the Independent Commission of Mines and Minerals (ICMM) and the Ministers in charge of Mining and Environment took place in Pristina.

Lydian has agreed to develop a systems-based approach to environmental, labor/social and community management as well as on relations with stakeholders.

The IFC PEP-SE (Private Enterprise Partnership- Southern Europe) - Technical Assistance team is involved, currently in the process of completing a scoping exercise in Kosovo involving Lydian, ICMM, the local authorities and other key stakeholders.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Client Documentation

File Name Actions
Final Environment and Social Action Plan.pdf
Lydian Resources Company Ltd Public Consultation and Disclosure Strategy.pdf