Date ESRS Disclosed

Apr 10, 2007

Country

Brazil

Region

Latin America and the Caribbean

Last Updated Date

Jun 3, 2021

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : Jun 22, 2007
Signed : Jun 27, 2007
Invested : Jan 3, 2008

Sector

Other Food

Industry

Agribusiness and Forestry

Department

Gbl Ind, Manufact, Agribus & Services

Project Description

The company has an investment program for 2007-2010 to expand its production and logistics capacity. The investment program includes:

- the expansion of its Extrema (state of Minas Gerais) and three of its Guarulhos (state of Sao Paulo) plants;
- the construction of a new distribution center and administrative offices in Guarulhos;
- the construction of a new plant, and
- incremental working capital.

Overview of IFC's Scope of Review

IFC’s review of this Category B project consisted of appraising Pandurata Alimentos Ltda.’s (or the company) own assessment of its environmental, occupational health and safety, labor and social development information as per:

- Prior to IFC’s appraisal following:

- Preparation of a preliminary environmental and social questionnaire (AIS) answering to IFC’s main points for concern, which guided the client in the organization presentation and documents to be submitted during appraisal mission.

- During IFC’s appraisal the following actions took place:

- Presentation by the company of the proposed investment;
- Presentation by the company on the Human Resources policy and actions and on Occupational Health and Safety issues;
- Presentation by the company of the Social assistance/responsibility area;
- Site visits to all plants by IFC’s environmental specialist to evaluate both social and environmental issues. Photographs of all plants were taken.
- The company submitted statistics on occupational health and safety issues, as well as on more general labor and social responsibility issues
- Meeting with the company’s suppliers procurement and quality assurance team.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement