Summary of Proposed Investment

Project Number

8437

Company Name

Grupo Calidra, S.A. de C.V.

Date SPI Disclosed

Oct 23, 1997

Country

Mexico

Industry

Manufacturing

Status

Completed

Sector

Miscellaneous and Industrial Ores (Including Magnesite, Fluorite, Sulfur, Soda Ash, Clays, Gypsum, Lime, Peat, Boron, Diatomite, Feldspar, etc.)

Department

Gbl Ind, Manufact, Agribus & Services

Environmental Category

B - Limited

Previous Events

Approved : Dec 18, 1997
Signed : Feb 10, 1998
Invested : Feb 26, 1998

Project Description

Summary Of Project Information (SPI)

Project NameMEXICO - Grupo Calidra, S.A. de C.V.
     
RegionLatin America and the Caribbean
Sector
Project No008437
Projected Board DateDecember 1, 1997
Company NameGrupo Calidra, S.A. de C.V.
Technical Partner and/or Major Shareholders

The Riefkohl family.

Project Cost Including proposed IFC investment

The total project cost is estimated at US$43.0 million. The proposed IFC investment would total US$28 million and would consist of (i) a US$12 million A loan and a US$6 million equity subscription both for IFC’s own account and (ii) a US$10 million B loan for account of participant banks.

Location of project and Description of site

Mexico. Project sites include various locations in different parts of Mexico. The greenfield facility will be located in Puebla.

Description of Company and Purpose of Project

The Company is the largest lime producer in Mexico. Lime is used extensively in the construction industry, in steel manufacturing, and in numerous other chemical and industrial applications. The purpose of the project is to assist the Company in the financing of: (i) the modernization and expansion of its existing facilities; and (ii) the construction of a greenfield lime plant.



Environmental Category and Issues

Environmental Unit has ranked this project a category “B” project. Environmental upgrades are underway at several of the Company’s plants. These activities and other commitments by Calidra will bring the existing operations into compliance with World Bank guidelines. The new plant in Puebla will be designed to meet the World Bank guidelines.

     

The is October 31, 1997 from the Public Information Center.

Date SPI sent to PIC      October 23, 1997

For Additional Information contact: Corporate Relations Unit -
telephone: (202) 473-7711
facsimile: (202) 676-0365
Environmental documents for this project are available at http://www.ifc.org and from the World Bank InfoShop (http://www.worldbank.org/html/pic/aboutinfo.html).

Sponsor / Cost / Location