Projects

Summary of Proposed Investment

Project Number

7907

Company Name

JY Estates Limited

Date SPI Disclosed

Feb 18, 1997

Country

Zambia

Industry

Agribusiness and Forestry

Status

Completed

Sector

Horticultural Products (Flowers)

Department

Regional Industry - MAS Africa

Environmental Category

B - Limited

Previous Events

Approved : Mar 24, 1997
Signed : Aug 15, 1997
Invested : Dec 2, 1997

Project Description

SUMMARY OF PROJECT INFORMATION

Project Name Zambia-JY Estates Limited

Region Sub-Saharan Africa

Sector Floriculture

Project No 007907

Projected Board Date March 31, 1997

Company Name JY Estates Limited

Technical Partner and/or Major Shareholders

  The project is jointly (50/50) owned by Michael Jones and Sharon Jones, a husband and wife team.  Mr Jones is a South African citizen who was born and grew up in Zambia.  He holds a Diploma in Agriculture. Mrs Jones is a Zimbabwean citizen with a degree in Education.

Project Cost Including Proposed IFC Investment

  The project is estimated to cost US$2.2 million and IFC has been requested to provide a loan of US$890,000.

Location of Project and Description of Site

  The project will be located on a 206 hectare farm in Chisamba, 60km north of Lusaka, Zambia.

Description of Company and Purpose of Project

 JY Estates Limited is a Zambian registered company which intends to establish a 5 hectare rose project at Kamwaysunka Farm in Chisamba.  JY has been successfully running a 3 hectare export rose project on the outskirts of Lusaka, Zambia for the last three years

Expected Developmental Impact

 IFC''s investment will contribute to the creation of 230 jobs comprising of 200 labourers and 30 administrative and management staff.  This will improve the quality of life of over 2,000 people in the surrounding areas.  The project will generate substantial foreign currency earnings for Zambia.  The project’s earnings will all be in foreign currency.

Environmental Category and Issues

This is an environmental review category B project. Environmental, occupational, health and safety issues include pesticides handling and application, integrated pest management, water supply, liquid and solid waste disposal, CFCs, disposal/destruction of pesticides and provision of personal protective equipment and framing. The sponsors have agreed to comply with applicable World Bank and Government of Zambia environmental requirements. The environmenal Review Summary is available from the Public Information Center.

Date SPI sent to PIC February 18, 1997

For additional information contact:  Corporate Relations Unit -   telephone:  (202) 473-7711 - facsimile:  (202) 676-0365.