PROJECT

Projects

Summary of Proposed Investment

Project Number

7320

Company Name

ASSAN DEMIR VE SAC SANAYI ANONIM SIRKETI

Date SPI Disclosed

Apr 8, 1997

Country

Turkiye

Industry

Manufacturing

Status

Completed

Sector

Aluminum

Department

Gbl Ind, Manufact, Agribus & Services

Environmental Category

B - Limited

Previous Events

Approved : Jun 4, 1997
Signed : Jun 20, 1997
Invested : Aug 1, 1997

Project Description

Summary Of Project Information (SPI)

Project NameTurkey-Assan II
     
RegionEurope
Sector
Project No007320
Projected Board DateMay 20, 1997
Company NameAssan Demir ve sac Sanayii A.S.
Technical Partner and/or Major Shareholders

Technical Partners: Fata Hunter (Italy) and Norandal (U.S.)

Project Cost Including proposed IFC investment

US$68.0 million including an IFC senior loan of US$10 million and quasi-equity of up to US$5 million.

Location of project and Description of site

The plant will be located in Tuzla, 30 km south east of Istanbul. The Company is an existing IFC client. Tuzla is within a major industrialized area and has good transportation and communication facilities.

Description of Company and Purpose of Project

The project is a US$68 million expansion and modernization of the aluminum sheet and foil businesses of Turkey’s leading manufacturer in the aluminum finishing sector. The Company’s principal products are aluminum coils, sheets and foil. The objectives of the project are to: (i) increase total aluminum production capacity to meet increasing demand and take advantage of market opportunities, and (ii) significantly reduce Assan’s operating costs by upgrading its technology to internationally competitive levels. The project consists of the purchase and installation of: (i) one casting line (Assan’s third); (ii) one cold mill (Assan’s second); (iii) four additional annealing furnaces; (iv) one foil line; and (v) related processing equipment.

Environmental Category and Issues

This is a category B project according to IFC’s environmental review procedure. Environmental issues include air emissions, liquid effluents, and solid waste disposal. Occupational and safety issues include exposure to high temperatures and potentially hazardous aerosols. Speed casting technology produces thin hot rolled sheets which reduce the number of passes for production of finished products by subsequent cold rolling. This would result in lower consumption of electrical energy per ton of finished product compared with conventional casting techniques. In November 1995, Assan and IFC signed an agreement to change the Company’s CFC foam for sandwich panels to non-CFC material by 1997. This project is on-going under the OTF Project Grant program. The Company has spent about US$0.6 million to date in this project.

The is from the Public Information Center.

Date SPI sent to PIC April 8, 1997

For Additional Information contact: Corporate Relations Unit -
telephone: (202) 473-7711
facsimile: (202) 676-0365
Environmental documents for this project are available at http://www.ifc.org and from the World Bank InfoShop (http://www.worldbank.org/html/pic/aboutinfo.html).

Sponsor / Cost / Location