PROJECT

Projects

Summary of Proposed Investment

Project Number

7057

Company Name

Siderurgica de Guatemala SA

Date SPI Disclosed

Sep 6, 1996

Country

Guatemala

Industry

Manufacturing

Status

Completed

Sector

Mini-Mills

Department

Gbl Ind, Manufact, Agribus & Services

Environmental Category

B - Limited

Previous Events

Approved : Nov 1, 1996
Signed : Dec 5, 1997
Invested : Jan 13, 1998

Project Description

Summary Of Project Information (SPI)

Project NameGuatemala - Sidegua S.A. (Sidegua)
    
RegionLatin America and Caribbean
Sector
Project No007057
Projected Board DateOctober 6, 1996
Company NameSidegua S.A. (Sidegua or the Company)
Technical Partner and/or Major Shareholders

Sidegua S.A. is 100% owned by Aceros de Guatemala S.A..

Project Cost Including proposed IFC investment

Project cost is estimated at US$51.6 million (of which US$38.2 million represent the construction of a power plant and the balance of US$13.3 million entails upgrading and modernizing the existing steel facilities. IFC’s total investment will be US$25 million (of which US$18 million A Loan, and US$7 million B Loan).

Location of project and Description of site

Escuintla Department, 67 kms south of Guatemala City, where Sidegua’s mini-mill is located.

Description of Company and Purpose of Project

Sidegua is a sister company within the Aceros de Guatemala Group (“ The Group ”). It manufactures billets, a key raw material for The Group’s final products, which are: rebars, profiles, sheets, wire and flats. The Group was established in 1963. It is the leading supplier of steel products in Guatemala and the only one with steel melting facilities producing from scrap the steel billets for the rolling mills.

Sidegua’s proposed US$51.6 million investment program to be implemented by mid 1998 will help the Company to reduce production costs and obtain a more streamlined and efficient plant configuration to meet the growing demand for its products.

Environmental Category and Issues

This is an environmental category B project according to IFC''s environmental review procedure.

The is from the Public Information Center.

Host country location of environmental documentsCentro de Energía Escuintla, Avenida de las Americas 18-81, Zona 14. Guatemala City, Guatemala.

Date SPI sent to PIC September 6, 1996 
For Additional Information contact: Corporate Relations Unit -
telephone: (202) 473-7711
facsimile: (202) 676-0365
Environmental documents for this project are available at http://www.ifc.org and from the World Bank InfoShop (http://www.worldbank.org/html/pic/aboutinfo.html).

Sponsor / Cost / Location