PROJECT

Projects

Summary of Proposed Investment

Project Number

28985

Company Name

Georgia Urban Energy LLC

Date SPI Disclosed

Apr 4, 2011

Country

Georgia

Industry

Infrastructure

Projected Board Date

Jun 16, 2011

Status

Completed

Sector

Large Hydro - Renewable Energy Generation

Department

Regional Industry INF LAC & EUR

Environmental Category

A - Significant

Previous Events

Approved : Jun 16, 2011
Signed : Jun 22, 2011
Invested : Dec 23, 2011

Project Description

The Project consists of the construction, operation and maintenance of an 87 MW run-of river hydro power plant (“HPP”), on the Paravani River, near the town of Akhalkalaki, Georgia, close to the Turkish border (the Project”). In addition to the power generation facilities, the Project includes a conveyance tunnel of 13.77km and 32 km of 220 kV transmission line to the Akhalskhe substation which connects to the 400/500 kV high voltage Akhalskhe-Borcka transmission line from Georgia to Turkey (the “Black Sea Transmission Project” or “BSTP”). The Project will supply electricity to the Georgian market in the three winter months (expected to be in December, January and February) and export power to the Turkish market in the remaining nine months of the year. Total Project cost is estimated at $156.5 million.

Sponsor / Cost / Location

Development Impact