Summary of Proposed Investment

Project Number

27396

Company Name

ZONA FRANCA CELSIA S A E S P

Date SPI Disclosed

Dec 23, 2008

Country

Colombia

Industry

Infrastructure

Projected Board Date

Mar 2, 2009

Status

Completed

Sector

Gas - Thermal Power Generation

Department

Gbl Infrastructure & Natural Resources

Environmental Category

B - Limited

Previous Events

Approved : Sep 21, 2009
Signed : Sep 30, 2009
Invested : Nov 13, 2009

Project Description

The project consists of the construction of a 169 MW gas-fired combined cycle unit by Termoflores S.A. E.S.P. (“Termoflores” or “the Company”), a generation company whose operations are located in Barranquilla, Colombia. Currently, Termoflores has three natural gas-fired units in operation, (the Flores I combined-cycle and the Flores II and III open-cycle) with a total installed capacity of 441 MW. Flores IV includes the expansion/conversion of the existing gas turbines in Flores II and III from open cycle to a combined cycle facility, by adding a new steam turbine generator, heat recovery steam generator and balance of plant equipment. Flores IV will utilize the waste heat from Flores II and III to provide 169 MW of additional capacity without using significant additional gas. After the project is completed, Termoflores will have two operating units (Flores I and Flores IV) with a generation capacity of 610 MW. The estimated construction time is 25 months and project completion must be attained before December 1, 2010.

The project was granted a fixed 10-year period reliability charge payable over the firm capacity provided by the project.