PROJECT

Projects

Summary of Proposed Investment

Project Number

26619

Company Name

AZITO ENERGIE SA

Date SPI Disclosed

Mar 30, 2012

Country

Cote D'Ivoire

Industry

Infrastructure

Projected Board Date

May 17, 2012

Status

Active

Sector

Gas - Thermal Power Generation

Department

Gbl Infrastructure & Natural Resources

Environmental Category

B - Limited

Previous Events

Approved : May 17, 2012
Signed : Oct 18, 2012
Invested : Mar 7, 2013

Project Description

The Project consists of the expansion of the existing 2x 144MW natural gas-fired open cycle Azito power plant in Côte d’Ivoire by adding 139MW steam cycle capacity, converting it into a combined cycle operation (the “Project”). The Project, expected to enhance the efficiency of the existing plant by generating 50 percent more power without the use of any additional gas, will be developed, designed, constructed and operated under a 20-year Build-Own-Operate-Transfer (“BOOT”) arrangement. The Project will sell its power to Government of Côte d’Ivoire (GOCI) through Compagnie Ivoirienne d’Electricité (“CIE”), the private transmission and distribution company.

Sponsor / Cost / Location

Development Impact