PROJECT

Projects

Summary of Proposed Investment

Project Number

26399

Company Name

CARUQUIA SA ESP

Date SPI Disclosed

Apr 21, 2008

Country

Colombia

Industry

Infrastructure

Projected Board Date

May 22, 2008

Status

Completed

Sector

Small Hydro (<10MW) - Renewable Energy Generation

Department

Gbl Infrastructure & Natural Resources

Environmental Category

B - Limited

Previous Events

Approved : Jul 21, 2008
Signed : Oct 16, 2008
Invested : Dec 19, 2008

Project Description

The project consists of the development, construction and operation of two small run-of-river hydropower plants in the Guadalupe river basin, 95 kilometers (km) north of the city of Medellin, in the Antioquia Department in western Colombia. The two plants, Caruquia S.A. (9.5MW) and Guanaquitas S.A. (9.8MW) are expected to begin commercial operations in late 2009 and early 2010, respectively.

Sponsor / Cost / Location

Development Impact