Project Description
The proposed IFC investment will extend corporate loans to EnerjiSA Enerji Üretim A.S. (EnerjiSA or the company), secured with its underlying portfolio of energy assets and contracts, to finance the first phase of EnerjiSA’s capital investment program for the 2008 to 2012 period. IFC’s proposed investment will be in parallel with financing arranged by the Turkish commercial bank Akbank and the European commercial bank WestLB headquartered in Germany.
The project consists of the construction of a portfolio of one natural gas-fired thermal plant (TPP) and – according to current planning – ten hydroelectric power plants (HPP) in various locations throughout Western and Southern Turkey with total capacity of approximately 1.9 GW with an estimated cost of $2.0 billion (EUR1.4 billion) (Phase I), representing the initial phase of Enerjisa’s overall capital investment aimed at developing 5.0 GW in generation capacity by 2015.