Project Description
The project is to build, own and operate three run-of-the-river power stations on the White Water River (or Bai Shui Jiang) in Yunnan Province, China. The project has a total installed capacity of 78 MW: 15MW for the first station (“BSJ I”), 15MW for the second station (“BSJ II”) and 48 MW for the third station (“BSJ III”).
The project has substantial development impact. IFC is providing investment and technical assistant support to a local Chinese sponsor who brings capital and project development capabilities to a less developed western region of China. The project is in line with the Government of China’s policy to develop the western interior of the country and to support the development of clean energy resources.