PROJECT

Projects

Summary of Proposed Investment

Project Number

20490

Company Name

Domicem S.A.

Date SPI Disclosed

May 9, 2003

Country

Dominican Republic

Industry

Manufacturing

Projected Board Date

Jun 13, 2003

Status

Completed

Sector

Cement

Date Revised SPI Disclosed

Mar 16, 2005

Department

Gbl Ind, Manufact, Agribus & Services

Environmental Category

B - Limited

Previous Events

Approved : Sep 26, 2003
Signed : Oct 3, 2003
Invested : Aug 18, 2004

Project Description

The project is to design, construct and operate a greenfield, integrated, dry process cement plant of 800,000 tons per year (tpy) clinker capacity and 900,000 tpy cement capacity at an estimated cost of $84 million in the Dominican Republic. The Domicem plant is expected to be commissioned by May 2005 and to sell 90% of its production in the domestic market and 10% as exports. As of March 16, 2005, there has been a modification to this project, which is covered under a new project, Domicem II – Project No.24209. Total Project Cost has also been revised to US$113.5 million.

Sponsor / Cost / Location

Development Impact