Project Number

50763

Company Name

Magazyn EE Turosn Koscielna Sp. z o.o.

Date SPI Disclosed

Dec 5, 2025

Country

Poland

Region

Europe

Projected Board Date

Jan 30, 2026

Environmental Category

B - Limited

Status

Pending Approval

Last Updated Date

Dec 9, 2025

Department

Regional Industry INF LAC & EUR

Industry

Infrastructure

Sector

Electric Power Other (Including Holding Companies)

Project Description

The proposed investment will support the development of two battery energy storage systems (BESS) with a capacity of 200MW (800MWh) each, one located near the city of Elk and the other near the village of Turosn in North-East Poland (the “Project”). Greenvolt Power Group Sp. z o.o. (“Greenvolt Power”) develops the Project. Greenvolt Power is part of the Portugal headquartered power company Greenvolt Energias Renovaveis S.A. (“Greenvolt”), which is positioned as a European leader in BESS with a total pipeline of 4.7 GW. Greenvolt is wholly owned by Kohlberg Kravis Roberts & Co. (“KKR”), a leading global investment firm.

The Project consists of the construction, operation, and maintenance of the two BESS. Construction work is expected to finish in April 2026 for the Elk project location and June 2026 for the Turosn project location. The Project is anticipated to be in operation for 19 years and operate in the Polish capacity market starting in 2028. It will also participate in the balancing and ancillary services markets, as well as the wholesale market. 