PROJECT

Projects

Summary of Investment Information

Project Number

50576

Company Name

ABYDOS SOLAR POWER COMPANY

Date SPI Disclosed

Dec 12, 2024

Country

Egypt, Arab Republic of

Region

Africa

Projected Board Date

Mar 13, 2025

Environmental Category

B - Limited

Status

Active

Last Updated Date

Jul 4, 2025

Department

Regional Industry - INF Africa

Industry

Infrastructure

Previous Events

Approved : Mar 13, 2025
Signed : Apr 9, 2025
Invested : Jul 1, 2025

Sector

Solar - Renewable Energy Generation

Additional Project Attributes

Blended Finance
Public-Private Partnerships

Project Description

 The project consists of integrating 300MWh Battery Energy Storage System (Abydos I BESS or the Project) into the existing 500MWac solar Photovoltaic (PV) Power plant, located in Aswan Governorate, Egypt, and financed by IFC in 2022 under Abydos Solar IPP project (Abydos I). Abydos I has recently completed construction and was commissioned on 29 November 2024.  The Project is governed under a long-term Power Purchase Agreement with the Egypt Electricity Transmission Company, fully guaranteed by Egypt’s Ministry of Finance.                                         

Associated Advisory Engagement

 IFC Sustainable Infrastructure Advisory is currently undertaking a gender assessment of AMEA Power, including a site-level gender assessment of the Project, as well as a corporate-level assessment of AMEA Power.

Sponsor / Cost / Location

Development Impact

E&S Category Rationale / Risks and Mitigation