39254
ELECNORTE S A S ESP
Jan 18, 2019
Colombia
Latin America and the Caribbean
Mar 19, 2019
A - Significant
Completed
Sep 30, 2021
Regional Industry INF LAC & EUR
Infrastructure
Approved : May 29, 2019
Signed : Oct 25, 2019
Invested : Dec 23, 2019
Electric Power Transmission
The proposed project entails the construction of a 138km, 100kv regional transmission line in La Guajira, Colombia (the “Project”).
Following an open tender process, the Colombian Energy Planning National Authority (UPME) awarded this Project to Elecnorte S.A.S (“Elecnorte” or the “Company”). The project comprises the design, construction, operation, and maintenance of the regional transmission line for 25 years and the refurbishment of three existing sub-stations.
For Inquiries About the Project, Contact
For Inquiries and Comments About IFC, Contact
Local Access of Project Documentation
Elecnorte SAS ESP
Carrera 7a No. 114 - 33 Of. 704, Bogota, Colombia
www.elecnorte.com