PROJECT

Projects

Summary of Investment Information

Project Number

38502

Company Name

EXCELERATE ENERGY BANGLADESH LIMITED

Date SPI Disclosed

Apr 14, 2017

Country

Bangladesh

Region

South Asia

Projected Board Date

May 15, 2017

Environmental Category

B - Limited

Status

Active

Last Updated Date

Feb 15, 2018

Department

Regional Industry - INF Asia & Pac

Industry

Metals and Mining

Previous Events

Approved : Jun 13, 2017
Signed : Jun 23, 2017
Invested : Feb 13, 2018

Sector

Oil and Gas Transport or Pipeline

Project Description

The project (the “Project”) comprises the development, construction, operation and transfer of an offshore marine terminal to support the transfer, storage and regasification of liquefied natural gas (“LNG”) for delivery to an onshore transfer location in Bangladesh. The Project’s guaranteed base load regasification rate is 500 million standard cubic feet per day (“mmscfd”) of natural gas.

The Project consists of a) fixed infrastructure – including a subsea plug connector and mooring system, a subsea pipeline to shore, and tie-in facilities to the onshore Moheshkhali-Anowara pipeline, b) a floating storage and regasification unit (“FSRU”) with a nominal storage capacity of 138,000 cubic meters of LNG to be chartered to the Project, and c) the provision of port services to support the transfer of LNG and operations.

The Project is being co-developed via a special purpose vehicle, Excelerate Energy Bangladesh Limited (the “Project Company”), by the International Finance Corporation (“IFC”) and Excelerate Energy Limited Partnership (“Excelerate” or the “Sponsor”).

Associated Advisory Engagement

 N/A

Sponsor / Cost / Location

Development Impact

E&S Category Rationale / Risks and Mitigation