37808
TOBENE POWER SA
Feb 16, 2017
Senegal
Africa
Mar 30, 2017
B - Limited
Active
Aug 10, 2017
CNGS6 - Gbl Infrastructure & Natural Resources/Infrastructure - CAF
Infrastructure
Approved : Jul 27, 2017
Signed : May 31, 2017
Invested : Aug 8, 2017
Heavy Fuel Oil - Thermal Power Generation
Public-Private Partnerships
The Tobene expansion project consists of an increase in the installed capacity of the existing Tobene IPP (an HFO fired power plant convertible to gas operations in Senegal) from 96 MW to 115 MW, such that under its Power Purchase Agreement with Senelec it will provide increased a minimum guaranteed capacity, from 70 MW to 105 MW, including 115 MW for the peak demand during the peak season (i.e June to October). The expansion was awarded to Tobene Power SA on a negotiated basis by the Government of Senegal following the successful completion of the existing Tobene, currently owned and operated by the same company.
For Inquiries About the Project, Contact
For Inquiries and Comments About IFC, Contact
Local Access of Project Documentation
Tobene Power disclosed the local ESIA in accordance with the Senegalese requirements and the document was made available to the DEEC (Department de l’Environnement et des Etablissements Classés).Documentation including background information updates was also made available during the ESIA.The EIA and ESIA are made available with this document and for further information on the project Tobene Power should be contacted as per the details above.