35701
NEPAL WATER AND ENERGY DEVELOPMENT CO PVT LTD
Jul 30, 2018
Nepal
South Asia
Sep 28, 2018
A - Significant
Active
Oct 28, 2022
Regional Industry - INF Asia & Pac
Infrastructure
Approved : Mar 21, 2019
Signed : Oct 28, 2019
Invested : Oct 25, 2022
Large Hydro - Renewable Energy Generation
Blended Finance
Public-Private Partnerships
Upper Trishuli 1 is a 216 MW run of river hydropower project on the Upper Trishuli river in Nepal (“UT1” or the “Project”), owned by a special purpose vehicle, Nepal Water & Energy Development Company Pvt. Ltd. (“NWEDC” or the “Company”) established under the laws of Nepal.
The Project will sell power to Nepal Electricity Authority (“NEA”), the national utility, for domestic supply under a 30-year power purchase agreement (“PPA”). The Project will be developed on a Build, Own, Operate and Transfer (“BOOT”) basis under a 35-year concession agreement (Project Development Agreement or “PDA”) with the Government of Nepal’s (“GoN”) Ministry of Energy, Water Resources and Irrigation (“MOWERI”).
The Project is of strategic national importance and will be the largest Foreign Direct Investment (“FDI”) in Nepal to date, increasing the country’s domestic power supply by approximately one-third compared to today’s levels and providing about 40% of its expected 1,456 GWh of net annual output during the dry season, which includes the peak winter demand months. The Project’s expected commissioning date is October 2023.
For Inquiries About the Project, Contact
For Inquiries and Comments About IFC, Contact
Local Access of Project Documentation
Company Office.