PROJECT

Projects

Summary of Investment Information

Project Number

35349

Company Name

DAEHAN WIND POWER COMPANY PSC

Date SPI Disclosed

Aug 4, 2017

Country

Jordan

Region

Middle East

Projected Board Date

Oct 19, 2017

Environmental Category

A - Significant

Status

Active

Last Updated Date

Dec 26, 2018

Department

Regional Industry INF MCT

Industry

Infrastructure

Previous Events

Approved : Sep 6, 2018
Signed : Sep 18, 2018
Invested : Oct 22, 2018

Sector

Wind Power - Renewable Energy Generation

Additional Project Attributes

Public-Private Partnerships

Project Description

The project consists of the construction, operation and maintenance of a 51.75MW (installed capacity) wind farm in Jordan's Tafila Governorate (the “Project”). The Project will be an Independent Power Producer, generating about 153 GWh annually for sale to the National Electric Power Company under a 20-year Power Purchase Agreement. Turbine supplier Vestas will be the Engineering, Procurement and Construction and the equipment Operations and Maintenance contractor. Construction is expected to begin in January 2018 and operations by mid-2019.

Sponsor / Cost / Location

Development Impact

E&S Category Rationale / Risks and Mitigation