Project Description
Gul Ahmed Wind Power Limited (GAWPL or the Company) is a special purpose vehicle set up to develop a 50MW wind power generation plant located in the Jhimpir Wind Corridor, Thatta District of Sindh province in Pakistan. The project involves engineering, design, procurement, construction, turbine erection, grid tie-in, commissioning and operation & maintenance of the 50MW wind power generation facility (the Project). The Project will be an independent power producer and will sell electricity to the National Transmission and Dispatch Company Limited (NTDC) under a 20-year Energy Purchase Agreement (EPA). NTDC’s payment obligations under the EPA will be guaranteed by the Government of Pakistan.
The Project is expected to generate an annual average of 154GWh of electricity (on a P50 basis as per independent engineer’s estimates).