PROJECT

Projects

Summary of Investment Information

Project Number

34359

Company Name

Niko Resources Ltd

Date SPI Disclosed

Nov 18, 2013

Country

South Asia Region

Region

South Asia

Projected Board Date

Dec 19, 2013

Environmental Category

A - Significant

Status

Active

Last Updated Date

Nov 30, 2016

Department

Gbl Infrastructure & Natural Resources

Industry

Metals and Mining

Previous Events

Approved : Dec 19, 2013
Signed : Dec 19, 2013
Invested : Dec 20, 2013

Sector

Oil and Gas Production (Includes Development)

Project Description

IFC has been asked by Niko Resources Ltd. (“Niko” or the “Company”) to consider providing financing together with some other investors to support the Company in the following areas:

To finance the capital expenditure program in the KG-D6 block in India, consisting of (i) work-over of existing wells in the D1-D3 field, (ii) the development of the R-cluster and Satellite fields, and (iii) upgrading the surface facilities;
To finance the capital expenditure plan in the Block 9 in Bangladesh, consisting of (i) two development wells, (ii) upgrading the production facility, and ( iii) installation of additional compression to arrest production declines; and
To restructure the Company’s debt by refinancing expiring debt instruments with loans of a longer maturity.

In addition to providing the financing, IFC together with other anchor investors plan to help improve the Company’s environmental and social management systems and corporate governance which are considered critical by the Company for a future growth.

Sponsor / Cost / Location

Development Impact

E&S Category Rationale / Risks and Mitigation