Summary of Investment Information

Project Number

33839

Company Name

VETROELEKTRANE BALKANA D.O.O

Date SPI Disclosed

Dec 19, 2014

Country

Serbia

Region

Europe

Projected Board Date

Sep 30, 2017

Environmental Category

A - Significant

Status

Completed

Last Updated Date

Nov 12, 2022

Department

Regional Industry INF LAC & EUR

Industry

Infrastructure

Previous Events

Approved : Oct 6, 2017
Signed : Oct 16, 2017
Invested : May 9, 2018

Sector

Wind Power - Renewable Energy Generation

Additional Project Attributes

Public-Private Partnerships

Project Description

The proposed investment involves providing debt financing for a 158 MW greenfield wind power plant, in the Kovin municipality Serbia (the “Project”). The Project is wholly owned by Vetroelektrane Balkana d.o.o - WEBG (the “Project Company”), a limited liability company incorporated in Serbia. The capital expenditure required to implement the Project amounts to approximately EUR 300 million. Construction of the project has commenced in 2017 and commercial operations are expected to begin by Q4 2018/Q1 2019. The Project is being primarily developed by Abu Dhabi Future Energy Company PJSC (Masdar) and the generated electricity will be sold to the Serbian guaranteed supplier of electricity i.e. Elektro Privreda Srbije (EPS) under a 12-year Power Purchase Agreement.

Sponsor / Cost / Location

Development Impact