PROJECT

Projects

Environmental & Social Review Summary

Project Number

53426

Company Name

Shadwan Wind Power S.A.E

Date ESRS Disclosed

Aug 28, 2026

Country

Egypt, Arab Republic of

Region

Africa

Last Updated Date

Aug 28, 2026

Environmental Category

A - Significant

Status

Pending Approval

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

The Shadwan Wind IPP Project (the “Project”) involves the development, financing, construction, operation, and maintenance of the 900MW Shadwan wind farm, a greenfield, utility-scale wind power development located in Ras Shukeir, Red Sea Governorate, Egypt. The Project is located within a designated renewable energy development area allocated by the Government of Egypt (GoE) to the New and Renewable Energy Authority (NREA) under Presidential Decree No. 628 of 2024. The Project is expected to deliver strong development impact in Egypt by expanding wind power capacity, helping reduce the average cost of electricity generation through the displacement of more expensive and carbon-intensive generation sources, contributing to greenhouse gas (GHG) emissions reductions and Egypt’s climate commitments, and enhancing power sector resilience through diversification of the country’s generation mix. The Project is being implemented by Shadwan Wind Power S.A.E. (“Shadwan”) an Egyptian incorporated special purpose vehicle owned by Scatec ASA (the “Sponsor”). The Project will supply the electricity generated to the national grid under a 25-year Power Purchase Agreement (PPA) with the Egyptian Electricity Transmission Company (EETC), guaranteed by Egypt’s Ministry of Finance. The total Project cost is estimated at US$700 million. IFC’s proposed investment comprises of an A Loan of up to US$100 million as well as risk management products including interest rate swap and cross-currency swap from its own account. The remaining debt will be provided by a mix of parallel Lenders. The Project site is situated approximately 22 km southwest of Ras Ghareb City and approximately 10 km northwest of Wadi Dara village and consists of mostly desert ground with sparse vegetation. No human habitation, grazing, or agriculture is observed on, or adjacent to the site. The Project occupies an area of approximately 90 km² within a broader 350 km² area allocated for renewable energy development. The Project will comprise of 83 wind turbine generators (WTGs) together with related infrastructure including turbine foundations, crane hardstands, underground electrical cabling, an onsite substation, operations and maintenance facilities, internal access roads and ancillary infrastructure. From the Shadwan substation, a 500 kV Overhead Transmission Line (OHTL), 45km long, will connect it to the S4 Gharb (West) Bakr substation which is connected to the National Electricity Grid. The detailed design, route, construction, and maintenance during operation of the OHTL lies with the EETC. The 500 kV OHTL is considered as an associated facility to the Project. The Project is being constructed under a turnkey Engineering, Procurement, and Construction (EPC) agreement with Egypt Scatec Operations Company EPC (“Scatec EPC”), which will act as the single point of responsibility towards the Project, coordinating the principal execution packages, including the wind turbines, Balance of Plant (BoP) engineering, BoP construction and the high voltage (HV) substation works. The principal contractors are: Envision for the supply and erection of the wind turbine generators (WTGs), Orascom for BoP works, Siemens/Arcon for substation works and TYPSA for engineering services (collectively “Contractors”). Early works construction works commenced in June 2026 and works are expected to continue for approximately 22 months. The first phase of commercial operation is estimated to commence end of November 2027 with 242 MW, reaching full 900 MW by April 2028. The Project is expected to generate approximately 2000 employment opportunities during peak construction, including approximately 300 skilled and 1,700 semi-skilled and unskilled positions as identified in the Environmental and Social Impact Assessment (ESIA). The construction phase also involves temporary infrastructure, including laydown areas, batching plants, construction camps, temporary offices, and material storage areas. As of this appraisal, Scatec EPC is also expected to serve as the Operations and Maintenance (O&M) contractor. During operation, a substantially smaller permanent workforce will be required for operations and maintenance activities.

Overview of IFC's Scope of Review

IFC’s environmental and social (E&S) appraisal of the proposed Project consisted of: (i) reviewing technical, Environmental, Social, Health, and Safety (ESHS) information made available by Scatec; (ii) review of Scatec’s corporate and project’s proposed Environmental and Social Management System (ESMS), policies, procedures and organizational arrangements, including labor, health and safety, security, stakeholder engagement and grievance management; (iii) engagement with the Sponsor and the Lenders’ E&S Advisor (LESA). Documents reviewed as part of the E&S appraisal included: the i) Environmental and Social Impact Assessment (ESIA) of the wind farm and OHTL; ii) Stakeholder Engagement Plan (SEP); iii) Critical Habitat Assessment (CHA); iv) Cumulative Effects Assessment (CEA); v) Biodiversity Action Plan (BAP); vi) Biodiversity Management Plan (BMP); vii) Active Turbine Management Program (ATMP); viii) Post-construction Fatality Monitoring Program (PCFM); and (ix) a Non-Technical Summary (NTS), amongst others. The contextual risk was appraised using IFC internal contextual risk screening tool. Contextual risks identified relevant to this Project type and location included security risks, water availability, hunting and trapping of several species of resident and migratory birds, gender representation, labor policies and working conditions, and labor-related risks in the supply chain. Based on the findings of the contextual risk screening, particular attention was placed on the above-mentioned risks throughout the appraisal.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ESIA_Scatec Shadwan_900MW_Wind Farm_Egypt Final- Clean.pdf
BAP_Scatec Shadwan_900MW_Egypt_Aug5th.pdf
CEA_Scatec Shadwan_900MW_Egypt_Aug3rd.pdf
CHA_Shadwan_900MW_Egypt_Aug11th.pdf
SEP_Scatec Shadwan_900MW_Wind Farm_Egypt.pdf
NTS_Scatec Shadwan_900MW Wind Farm_Egypt.pdf
Shadwan 900MW Wind Farm OHTL ESIA.pdf