PROJECT

Projects

Environmental & Social Review Summary

Project Number

52751

Company Name

West Power Investments SRL

Date ESRS Disclosed

Apr 1, 2026

Country

Romania

Region

Europe

Last Updated Date

Apr 1, 2026

Environmental Category

A - Significant

Status

Pending Approval

Sector

Solar - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

Rezolv Energy is a renewables developer and independent power producer (IPP) headquartered in Czechia. The Sponsor has established West Power Investments S.R.L. (Sponsor) acting as the Project Special Purpose Vehicle (SPV) and which is wholly owned by Rezolv Energy.

The Sponsor seeks a loan of Euro 107 million from IFC to fund the construction and operation a large-scale photovoltaic (PV) power generation located in northern Arad County, Romania, within the administrative territories of Graniceri and Pilu communes (The Project). The Project comprises the design, construction, operation and eventual decommissioning of a ground-mounted solar photovoltaic installation together with associated grid connection infrastructure required to export electricity into the Romanian transmission system. The Project has an estimated installed DC capacity of 1.2 GWp. Electricity generated by the PV plant will be evacuated through a dedicated underground high-voltage infrastructure connecting the facility to the existing Nadab - Bekescsaba 400 kV overhead transmission line (OHTL) operated by Transelectrica S.A., the Romanian Transmission System Operator. The Project will be made up of the following principal components:

(i) Ground-mounted PV module arrays installed on fixed mounting structures (metallic fixed substructures)
(ii) Inverter stations converting direct current (DC) electricity into alternating current (AC)
(iii) Internal medium-voltage electrical collection network
(iv) Internal access roads and drainage infrastructure
(v) Main Step-Up Substation (MSUS)
(vi) 400 kV Interconnection Substation (ICS) “Graniceri”
(vii) Approximately 3.5 km underground high-voltage cable between substations
(viii) Control, telecommunication and SCADA systems.

The development is structured as a phased implementation enabling progressive construction and commissioning while ensuring compliance with grid requirements and environmental permitting conditions.

Land required for the Project and all principal components has been secured through voluntary transactions and servitude agreements. The Project does not require physical displacement of people or residential structures, and no involuntary resettlement or significant economic displacement is anticipated.

Construction activities are expected to commence following Engineering Procurement and Construction (EPC) contract signing and Notice to Proceed (NTP), anticipated in Q3 2026 and the total construction phase will take approximately 2.5 years with commercial operation date (COD) envisaged in H1 2028.

Overview of IFC's Scope of Review

IFC’s E&S appraisal comprised (i) a review of; 1) corporate E&S policies and procedures made available by the Sponsor; 2) the Independent Environmental and Social Consultant’s (IESC) appraisal report of the project and (ii) an in-person appraisal visit on January 12 to 14, 2026 to the site during which meetings were held with the Sponsor’s Environmental and Social team, including the Community Liaison Officer (CLO), project development team and the original project developer. Separately, engagement meetings were held with the Mayor of Arad County Council, the Mayors of Graniceri and Pilu Communes, and a group of local residents in Graniceri to discuss the project. A further follow-up meeting was held on January 22, 2026 with the Milvus Group, Bird and Nature Protection Association, a Romanian based non-governmental organization (NGO) .

IFC’s E&S scope of review was limited to the solar PV project as described in the section above.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Dama Solar PV_ Livelihood Restoration Plan.pdf
Dama Solar PV_Biodiversity Action Plan.pdf
Dama Solar PV_Construction Environmental and Social Management Plan.pdf
Dama Solar PV_Critical Habitat Assessment.pdf
Dama Solar PV_Environmental and Social Impact Assessment.pdf
Dama Solar PV_Stakeholder Engagement Plan.pdf
Dama Solar PV_Supplementary Lenders Information Package.pdf