PROJECT

Projects

Environmental & Social Review Summary

Project Number

52692

Company Name

Jordan CCGT IPP

Date ESRS Disclosed

Sep 17, 2026

Country

Jordan

Region

Middle East

Last Updated Date

Sep 21, 2026

Environmental Category

A - Significant

Status

Pending Approval

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The proposed IFC investment comprises an IFC A-loan of up to US$200 million supplemented by mobilized financing and hedging arrangements. This financing will support the development of a greenfield Combined Cycle Gas Turbine (CCGT) power plant located in the Mafraq district of Jordan, approximately 50 km southwest of Irbid city center, with an installed net capacity of about 700 MW (the Project), and an estimated total project cost of about US$900 million.
The project will be implemented through a special-purpose vehicle called “Sharikat Ak Khanasri Lil Taqa PSC” (the "Company") responsible for the design, construction, operation, and maintenance of the plant. The company has secured a 25-year Power Purchase Agreement (PPA) with the National Electric Power Company (NEPCO). The project is being developed by Etihad Development company (EDC or the "Sponsor"), a wholly owned subsidiary of UAE Etihad Water & Electricity ("EtihadWE"). EDC will be the main shareholder and controlling sponsor in the Project Company, alongside other partners still being selected by EDC.
Construction activities are expected to commence by end of 2026 and last for approximately 2 years. The main project facilities will include: three gas turbines (GTs); three heat recovery steam generators (HRSGs); one steam turbine generator; and one air-cooled condenser (ACC). Auxiliary components will include feedwater system; closed cooling water system; fogging & high fogging systems; water treatment plant; wastewater handling facilities; natural gas system; backup fuel system; and black start diesel generator.
The Associated Facilities of the project include: (i) ~7 km transmission line (400 kV) and substation connecting the plant to the national grid; (ii) ~300 m natural gas pipeline connecting the plant to the existing gas network; and (iii) ~4.5 km water supply pipeline from the existing water system to the plant.

Overview of IFC's Scope of Review

IFC’s environmental and social due diligence included a review of project documentation, information provided by the sponsor, and findings from an independent environmental and social due diligence (ESDD). Key documents reviewed included the environmental and social impact assessment (ESIA), environmental and social management plan (ESMP), stakeholder engagement plan (SEP) and project grievance mechanism, gender and human rights risk assessment, critical habitat screening, Land Acquisition Framework, and the sponsor’s existing human resources policies and procedures. In addition, IFC, together with other prospective lenders, engaged an independent lender’s environmental and social advisor (LESA) to undertake an ESDD of the project. The ESDD included a site visit in July 2026, during which the LESA team and IFC and other lenders assessed project conditions, reviewed environmental and social (E&S) risks and impacts, and evaluated the project’s alignment with applicable lender requirements.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Land Acqusition Framework_Mafraq CCGT Thermal Power Plant.pdf
Mafraq_700MW_CCGT_Non_Technical_Summary_Draft_REV0.pdf
ESIA_MafraqCCGTProject_Clean_REV3.pdf