PROJECT

Projects

Environmental & Social Review Summary

Project Number

52106

Company Name

Fertil Pampa S.A.U.

Date ESRS Disclosed

Sep 10, 2026

Country

Argentina

Region

Latin America and the Caribbean

Last Updated Date

Oct 19, 2026

Environmental Category

A - Significant

Status

Pending Approval

Sector

Nitrogenous Fertilizer

Industry

Manufacturing

Department

Regional Industry MAS LAC & EUR

Project Description

Fertil Pampa S.A.U. ("Fertil Pampa" or the "Company") is a special purpose vehicle wholly owned by Pampa Energia S.A. ("Pampa" or the "Sponsor"), established to develop a greenfield urea production complex in Bahia Blanca, Province of Buenos Aires, Argentina (the "Project"). Pampa is Argentina's largest integrated energy company, with operations spanning power generation, oil and gas, and electricity transmission and distribution.

The Project will be located on an 80-hectare site within the Ingeniero White port complex, adjacent to Pampa's existing power generation assets, with access to natural gas supply, high-voltage transmission infrastructure, seawater intake facilities, and a deep-water export port. The nearest community is located at approximately 600 m northwest of the boundary of the Project property line, with no communities located at least 8 to 10 km to the south and west. The Project comprises: (i) an ammonia and carbon dioxide production unit with capacity to produce 3,450 metric tons per day (“MTPD”) of ammonia and 4,400 MTPD of CO2; (ii) two parallel urea production trains with a combined production capacity of 6,000 MTPD of granulated urea; (iii) auxiliary facilities for seawater treatment, compressed air, steam, and nitrogen production; (iv) storage facilities, including an ammonia tank with a 20,000 ton capacity and a granulated urea silo with a 200,000 ton capacity; and (v) logistics infrastructure for the dispatch of urea by truck and ammonia and urea by vessel. Construction will be carried out under an engineering, procurement, and construction (“EPC”) contract over 4 years, generating an estimated 3,500 jobs during construction and 300 permanent jobs during operations.

The proposed investment consists of an IFC A/B loan package of up to US$750 million, comprising an IFC A Loan of up to US$300 million for IFC's own account and a B/Parallel Loan of up to US$450 million to be mobilized from commercial banks and other development finance institutions. IFC's financing will support the design, construction, operation, and maintenance of the Project, which is expected to increase domestic fertilizer production, reduce reliance on urea imports in the Southern Cone (Argentina, Brazil, Paraguay, and Uruguay), and contribute to regional fertilizer supply security.

Overview of IFC's Scope of Review

IFC's Environmental and Social ("E&S") review of the Project included an appraisal site visit conducted in May 2026 to the Project site in Bahia Blanca and its surrounding area of influence. IFC’s review comprised of: (i) meetings with Fertil Pampa's and the Sponsor's management team, including representatives from Environment, Occupational Health and Safety ("OHS"), Human Resources ("HR"), Community Relations; (ii) review of the Project's Environmental and Social Impact Assessment ("ESIA") and supporting technical studies, including the Cumulative Impact Assessment ("CIA"), Critical Habitat Assessment ("CHA"), among others; (iii) evaluation of the proposed environmental management measures, including air emissions, greenhouse gas ("GHG") emissions, seawater intake and effluent discharge, water resource use, and waste management; (iv) assessment of labor and working conditions across direct and contracted workers, including OHS and process safety management during the construction and operation phases; (v) review of community health, safety, and security aspects, including emergency preparedness and response, hazardous materials management, and traffic and road safety associated with construction and operational logistics; (vi) evaluation of the Project's stakeholder engagement process, information disclosure, and grievance mechanisms, including policies for the prevention of gender-based violence (“GBV”) and sexual exploitation, abuse, and harassment ("SEAH"), which included meetings with community members, Civil Society Organizations (“CSOs”) and representatives of local government institutions; and (vii) assessment of biodiversity and living natural resources in the Bahia Blanca estuary, including potential impacts on protected areas, critical habitat, and artisanal fisheries.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
PAMPA-EIA Planta Fertilizantes-Resumen Ejecutivo.pdf