PROJECT

Projects

Environmental & Social Review Summary

Project Number

52011

Company Name

HELIOS TOWERS PLC

Date ESRS Disclosed

Sep 1, 2026

Country

Africa Region

Region

Africa

Last Updated Date

Sep 2, 2026

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Mar 12, 2026
Signed : Mar 16, 2026
Invested : Apr 1, 2026

Sector

Engineering Services

Industry

Telecommunications and Technology

Department

INR Africa East Southern

Project Description

Helios Towers plc (“HT” or the “Company”) is a London-listed tower infrastructure company and a leading provider of mobile tower and passive telecommunication infrastructure across Africa and the Middle East. The company owns and operates over 14,000 sites in nine countries including Tanzania, DRC, Ghana, Congo Brazzaville, Senegal, South Africa, Madagascar, Malawi, and Oman (altogether, “OpCos”), serving mobile network operators under long-term contracts. Helios Towers has invited IFC to act as anchor investor in its March 2026 bond issuance (alongside other DFIs) for an amount of up to US$500 million. (the “Bond Issuance”

Helios Towers is a long-term client of IFC whose investments in Helios Towers and Helios Towers Africa (IFC projects 26627 and 29627), were disclosed as far back as March 27, 2009 and May 6, 2010 respectively. The third investment (IFC Equity project 34963) was disclosed on October 20, 2015 at https://disclosures.ifc.org/#/projectDetail/ESRS/34963. In 2020, the board approved a fourth investment in the form of a debt package of up to US$200 million from IFC’s own account and up to US$225 million in mobilization or parallel loans to support HT’s expansion in Africa, with loans extended to country-specific operating companies (OpCos). Building on this debt package, in May 2024, HT invited IFC to serve as anchor investor in its US$850 million bond issuance (HT Bond #46711), alongside other development finance institutions (DFIs). The 2020 and 2024 transactions had the same project scope and same environmental and social (E&S) risk profile hence the ESRS initially disclosed in 2020 was updated in May 2024 and redisclosed: https://disclosures.ifc.org/project-detail/ESRS/44602/hta-debt on 25 October 2025.

The proposed IFC investment comprises a bond subscription in an amount up to US$10 million as an anchor investor in the Bond Issuance for an amount of up to US$500 million. Proceeds from this corporate-level bond will support the Company to refinance outstanding convertible bond and term loans that are maturing in the near term (2027 and 2028 respectively) in addition to general corporate purposes.

Overview of IFC's Scope of Review

IFC’s Environmental and Social (E&S) review of this investment included both virtual engagements between December 2025 and January 2025 and a site visit coupled with documents review in February 2026 marked by: (i) three meetings with HT’s E&S management team; (ii) an assessment of annual E&S monitoring reports from the previous IFC investment; and (iii) a thorough evaluation of HT’s E&S policies and procedures. Additionally, IFC performed a site supervision visit at Ghana OpCo as part of its annual oversight program to corroborate findings from the virtual meetings. Furthermore, the review was supported by E&S due diligence, carried out by an independent E&S consultant who visited HT operations in DRC and Senegal to evaluate the maturity of HT’s Corporate E&S management system and its implementation across various OpCos. According to the 2026 supervision records, HT's E&S performance remains satisfactory.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan