IFC’s appraisal considered the environmental and social management planning process and documentation for the Project and gaps, if any, between these and IFC’s requirements. Where necessary, corrective measures, intended to close these gaps within a reasonable period of time, are summarized in the paragraphs that follow and (if applicable) in an agreed Environmental and Social Action Plan (ESAP). Through implementation of these measures, the Project is expected to be designed and operated in accordance with Performance Standards objectives.
PS1: Assessment and Management of Environmental and Social Risks and Impacts
Environmental and Social Policy and Management System. At corporate level, IWA has policies on environment, health and safety, sustainability and business ethics. These policies set out its commitment to quality, its principles of business conduct, its procedures for identifying and managing E&S risks, and the organizational arrangements for implementing them. They are broadly aligned with the IFC Performance Standards (PSs) and apply to all IWA projects. IWA’s management system is certified to ISO 9001. IWA will develop and implement a project-specific ESMS that builds on these corporate requirements and sets out the actions needed to meet the PSs, the WBG EHS Guidelines and national legislation. The project ESMS will cover Phase 1 and the site-wide aspects shared with Phase 2 (land, stakeholder engagement and grievances, security, shared infrastructure and cumulative impacts). It will include a legal and permit register maintained throughout the Project lifecycle (ESAP #1).
Identification of Risks and Impacts. IWA has prepared an ESIA covering the combined hybrid facility: the solar PV plant, the BESS, the Phase 2 wind component, the 33/225 kV substation, the SOMELEC grid connection and associated infrastructure, including access roads. The ESIA assesses baseline conditions (including air quality, noise, traffic, soils, hydrology and waste), project alternatives, and climate change and extreme weather risks across site preparation, construction, operation and decommissioning. It is supported by the Livelihood Restoration Plan (LRP), the Stakeholder Engagement Plan (SEP), which includes a grievance mechanism, and a framework Environmental and Social Management Plan (ESMP) with a monitoring program, to be updated at the end of the avifauna monitoring program (see PS6). The ESIA and the LRP were disclosed through public meetings with local and national authorities in 2025.
Management Programs. The framework ESMP summarizes the E&S management plans, including mitigation and monitoring measures for the construction and operation phases. For Phase 1, day-to-day management of E&S risks will rest with the EPC contractor, which is responsible for both construction and O&M. The ESMP requirements will be implemented through contractor-specific Construction and Operation E&S Management Plans (CESMP and OESMP) covering labor and working conditions, worker accommodation, community health and safety, traffic and transport, biodiversity, water, waste and wastewater, pollution prevention, emergency preparedness and stakeholder engagement. The CESMP and OESMP will be subject to review and approval by IWA prior to mobilization, and the OESMP will include a high-level decommissioning strategy (ESAP #2). As Phase 2 will be built by a different EPC contractor on a site where Phase 1 is operating, IWA will prepare an interface management plan covering simultaneous operations, including OHS, traffic and abnormal loads on the shared access road, security, emergency response, grievances and the connection works at the Project substation (ESAP #7).
Organizational Capacity and Competency. IWA's organogram defines E&S roles and responsibilities at SPV and contractor level. SPV-level resources currently comprise an E&S Director and an industrial relations/HR specialist. To strengthen its capacity for the Project, IWA will appoint a dedicated Project E&S Manager, a Community Liaison Officer (CLO), a specialist to oversee LRP implementation and monitoring, a biodiversity specialist to oversee the avifauna monitoring program and cumulative biodiversity impacts, and adequate EHS supervision during construction. For Phase 1, the EPC contractor will be required to submit an E&S staffing plan for IWA approval and to appoint qualified E&S personnel, including an E&S manager and EHS/OHS officers commensurate with the Project risk profile (ESAP #3).
Monitoring and Review. IWA's corporate ESMS requires regular monitoring and reporting of E&S performance across projects and contractors, including inspections by trained personnel across the area of influence of construction activities, internal audits by IWA's corporate HSSE and HR functions, and external third-party audits. A project-level monitoring and reporting framework, covering performance reviews, incident reporting, audits and corrective action tracking, will be established for construction and operation as part of the project ESMS and implemented through the CESMP and OESMP (ESAP #1 and #2).
Emergency Preparedness and Response. The ESIA hazard study identified the following major accident scenarios: for Phase 1, fire in electrical equipment and thermal runaway leading to fire or explosion in BESS containers; and, for Phase 2, wind turbine generator (WTG) collapse, projection of blades or blade fragments, and falling components. IWA's corporate ESMS requires emergency response plans to be updated for each project phase. At project level, the EPC contractor will prepare site-specific Emergency Preparedness and Response Plans (EPRPs) addressing these scenarios, as well as climate-related events such as heatwaves and floods. During Phase 2 construction and operation, emergency arrangements will be coordinated across the shared site through the interface management plan (ESAP #7). The EPRPs will include communication protocols to alert local authorities, communities and management, evacuation procedures, and regular training and drills (ESAP #2).
Cumulative Impacts. Phases 1 and 2 will share Project infrastructure, so Phase 2 impacts are considered cumulative impacts within the Project’s area of influence, in line with PS1. The ESIA includes a cumulative impact assessment (CIA) covering both phases within a 50 km area of influence, taking into account the existing wind and high-voltage transmission infrastructure, the Rocade ring road and the adjacent used-battery recycling facility. While shadow flicker from Phase 2 is predicted to remain within reference thresholds, screening-level modelling indicates that WTG noise could exceed the WBG EHS night-time guideline values at the nearest dwellings. Before Phase 2 construction starts, IWA will update the CIA to: (i) cover the worker accommodation, the access road and social valued environmental and social components (VECs), such as pastoral access; (ii) undertake detailed noise modelling for the final WTG layout and define mitigation to meet the WBG EHS guideline values; (iii) assess noise and shadow flicker effects on pastoralists and livestock; (iv) assess bird and bat collision risk, based on the avifauna monitoring results; and (v) define a framework for managing and monitoring cumulative impacts, with clear roles for IWA and the Phase 1 and Phase 2 contractors. IWA will keep the 420 m blade-projection safety zone free of dwellings and sensitive uses, implement the mitigation measures within its control and report on their implementation to IFC (ESAP #7).
Supply Chain. IWA will directly procure the PV modules, string inverters and BESS units for the Project. It has a formal procurement process, including vendor pre-qualification and selection procedures, and a Supplier Code of Conduct that sets out its E&S requirements, including on labor practices and human rights. These requirements are incorporated into supply contracts. IWA will incorporate a Human Rights Due Diligence Policy into a Supply Chain Management System (SCMS) for the Project and apply it to the procurement of critical equipment and materials, with a focus on forced labor risk (ESAP #4). For other materials and services, supply chain management will rest with the EPC contractor under IWA's procurement and E&S oversight, with traceability and sourcing requirements set out in the EPC contract (ESAP #2).
PS2: Labor and Working Conditions
For Phase 1, the construction workforce is expected to peak at about 100 workers during the 12-month construction period, of whom about 50 will be unskilled workers recruited locally. Around 10 workers will be employed during operation. Unskilled positions will be filled locally as far as possible, while specialized installation, testing and commissioning activities are expected to rely on foreign technicians mobilized by the EPC contractor and equipment suppliers.
Human Resources Policies and Procedures. IWA has corporate HR policies defining its approach to human resources in line with Mauritanian labor law and PS2. IWA's Code of Conduct commits the company to oppose all forms of slavery, forced labor, trafficking, illicit forms of child labor and human rights violations across its operations; to oppose discrimination on the basis of color, nationality, ethnicity, gender, age, sexual orientation, disability, religion or belief, with zero tolerance for sexual harassment; to achieve zero harm for employees; and to apply supply chain due diligence requirements. These requirements will be operationalized through a project HR Manual describing employment terms, working hours, wages, overtime, benefits, equal treatment of migrant workers, and disciplinary and grievance procedures, reflected in written contracts with employees. The Manual will be prepared in Arabic and French and communicated to all workers, including those engaged by contractors (ESAP #5).
Workers' Organizations. IWA's HR policy recognizes freedom of association and collective bargaining as a right of all employees, consistent with the Mauritanian Labor Code. Employees have the right to join trade unions or form workers' organizations without discrimination.
Grievance Mechanism. IWA operates a corporate grievance mechanism through which employees can report violations of labor law or the Code of Conduct. A site-level worker grievance procedure, managed by IWA, will be developed and made available to all project workers irrespective of employer. It will set out objectives, submission channels (including on-site suggestion boxes), grievance tiers and timelines, and roles and responsibilities, and will include a dedicated, survivor-centered channel for GBVH-related grievances (ESAP #5).
Child and Forced Labor. IWA maintains a strict prohibition on child and forced labor across its corporate policies and supply chain, consistent with PS2. The EPC contractor will implement these prohibitions on site, including age verification and audit procedures, through the CESMP and OESMP.
Occupational Health and Safety. OHS risks are expected to be significant given the scale of construction activity, the site location and climatic conditions, heavy lifting, work at height, traffic and transport movements, the establishment of worker accommodation, and extensive reliance on contractors and subcontractors in both phases.
OHS requirements will be reinforced and monitored through the contractor management plan described under PS1 (ESAP #1). The CESMP and OESMP will address hazard identification and risk assessment, safe systems of work, emergency response, training, incident reporting and OHS monitoring, and will include heat stress management: worker awareness of hydration and heat-related symptoms, work-rest scheduling during high-temperature periods, and provision of drinking water, shaded rest areas and appropriate personal protective equipment (ESAP #2). Additional OHS risks identified in the ESIA include exposure to electromagnetic fields near high-voltage equipment and work in confined spaces. Work at height and heavy lifting during WTG erection in Phase 2 will be managed through the interface management plan where they affect Project workers or the operating Phase 1 site (ESAP #7). Given the Project's reliance on contractors and subcontractors, IWA will commission periodic independent labor and OHS audits during construction (ESAP #5).
Workers' Accommodation. All workers will be housed in Nouakchott, and the EPC contractor will provide daily transport to and from the site. On-site facilities will be limited to offices, a canteen and sanitary facilities. IWA will require the EPC contractor to submit a workers' accommodation plan before mobilization, for inclusion in the CESMP. The plan will cover the selection and inspection of housing against IFC/EBRD guidance on workers’ accommodation, together with worker transport safety and the on-site welfare facilities (ESAP #5).
PS3: Resource Efficiency and Pollution Prevention
Resource Efficiency. The Project will use a SCADA system for real-time monitoring of operational data and an Energy Management System to coordinate generation sources, optimize energy flows and storage, and maintain compliance with grid requirements. A preventive maintenance plan covering the facility lifecycle, including periodic inspection and replacement of defective components, will form part of the project ESMS (ESAP #1).
Greenhouse Gas Emissions. Direct GHG emissions during construction will be minimal and short-term, arising mainly from fuel use in generators, vehicles and machinery. Although not quantified, they are expected to be well below 25,000 tCO2e per year. Phase 1 is estimated to avoid approximately 185,000 tCO2e per year, based on annual generation of about 308,000 MWh, rising to about 317,000 tCO2e per year once Phase 2 is operational. Fuel use and GHG emissions will be monitored under the project monitoring framework (ESAP #1).
Water Consumption and Availability. Water demand will be highest during construction, for the workforce and camp, concrete works and dust suppression. During operation, PV modules will be cleaned by dry robotic systems, with wet cleaning limited to occasional events (estimated at no more than twice a year) when dust adheres after rain or high humidity. Given the arid setting and the sensitivity of the shallow aquifer on which semi-nomadic communities rely, the Project will assess water supply options, covering yield and availability, permitting, potential competition with community use and treatment needs, in consultation with communities and authorities. The selected option will be reflected in the ESMS and contractors' plans (ESAP #6).
Stormwater and Drainage. Changes to ground cover and topography will affect site hydrology and downstream runoff, including temporary ponds that provide seasonal livestock watering and habitat for amphibians and waterbirds (see PS5 and PS6). The EPC contractor will manage stormwater and erosion in line with Good International Industry Practice (GIIP) and the WBG EHS Guidelines. The detailed drainage design will be sized for intense short-duration storms under climate change scenarios, control erosion and sediment transport, prevent the discharge of contaminated runoff and, where feasible, maintain or replace the watering function of the ponds (ESAP #6).
Wastewater. Sanitary wastewater will be generated during construction and operation, including from worker accommodation. As no off-site treatment is available near the site, the Project will assess on-site treatment options, including packaged treatment plants, and incorporate the selected solution, together with permitting, effluent quality controls and monitoring, into the ESMS, CESMP and OESMP (ESAP #6).
Waste Management. The Project will generate non-hazardous waste (packaging, construction debris and domestic waste) and hazardous waste (used oils, lubricants, chemicals, damaged PV modules and e-waste), in low overall volumes. As Mauritania has no licensed hazardous waste disposal facility, including for PV modules and e-waste, hazardous waste will be stored temporarily on site in designated, leak-proof areas pending removal by a qualified service provider. Non-hazardous waste will be disposed of at the Nouakchott engineered landfill (CET), about 25 km east of the city, through a licensed contractor.
The EPC contractor will develop a waste management plan aligned with Mauritanian legislation, the WBG EHS Guidelines and PS3, covering waste minimization, reuse and recycling, segregation, storage, tracking, transport and disposal, the selection of third-party contractors, and the management of damaged and end-of-life PV modules (ESAP #2).
Hazardous Materials. Given the shallow aquifer, fuel and hazardous material storage areas will be impermeable and bunded, with secondary containment of at least 110 percent of the largest container. Spill prevention and response procedures, including for contaminated firewater, will be included in the CESMP and OESMP (ESAP #2).
Air Quality and Noise. Dust from earthworks and vehicle movements, particularly on unpaved access routes, is the main air quality risk during construction. Construction noise will arise from machinery and vehicle movements and will be minimal during operation. Both will be managed through pollution prevention measures in the CESMP and OESMP (ESAP #2). Cumulative noise and shadow flicker from Phase 2 are addressed under Cumulative Impacts (PS1).
PS4: Community Health, Safety and Security
The Project is located in a sparsely populated area. The main settlements of Nouakchott are about 3.5 km from the site, while the village of Tackzeinite and isolated dwellings lie about 385 m from the site boundary. The Project may nevertheless pose community health and safety risks given its scale, the equipment and materials used, and the continued movement of semi-nomadic pastoralists and their livestock through and around the site. Construction risks include traffic and road safety, worker-community interactions, noise and GBVH associated with the construction base. Operational risks include electrical and fire hazards associated with the BESS. Cumulative noise and shadow flicker from Phase 2 are addressed under Cumulative Impacts (PS1).
Community health and safety measures, including the prevention of and response to GBVH and awareness-raising on sexually transmitted infections for workers and communities, will be set out in Community Health and Safety Management Plans forming part of the CESMP and OESMP (ESAP #2).
Traffic and Transport. Construction traffic will be dominated by equipment deliveries from the Port of Nouakchott, creating risks for communities and for livestock crossing the access road. Phase 2 will add abnormal loads (blades about 71 m long) on the same route, including the Project access road. The Project will undertake a transport risk assessment and, based on its findings, develop a Traffic and Transport Management Plan defining delivery routes and safety measures (ESAP #2), which will be extended to Phase 2 deliveries through the interface management plan (ESAP #7).
Infrastructure and Equipment Safety. Risks may arise from unsafe design, unauthorized access or inadequate management of safety exclusion zones in an area used by pastoralists and livestock. The PV and BESS area will be fenced and guarded, and public exposure to electromagnetic fields is expected to be negligible beyond the site fence and substation. The Project will apply GIIP in design, construction and operation, and safety considerations will be integrated into the ESMS, CESMP, OESMP and emergency response arrangements once the detailed design is finalized (ESAP #1 and #2).
Security. The PV and BESS area will be fenced, with access control and perimeter patrols provided by unarmed guards from a licensed private security company. IWA will develop a security management plan, including a code of conduct for security personnel covering non-discrimination, sexual harassment and GBVH, interaction with local communities and the proportionate use of force (ESAP #1).
PS5: Land Acquisition and Involuntary Resettlement
Displacement Impacts. The Project site is state land located in a peri-urban area of Nouakchott, characterized by agro-pastoral land use and ongoing urban expansion, where camel pastoralists move seasonally across and around the site. The Project has resulted in the physical displacement of one household and the economic displacement of 25 households (203 people in total), as well as one agricultural cooperative with 67 members. Losses comprise 49 structures and related assets (tents, huts, sheds, four permanent rooms, toilets, fences, a solar-powered irrigation well, a borehole and a small, occasionally used mosque), about 35 ha of cultivated land, of which 33 ha is farmed by the cooperative, and the income of five livestock convoyers whose clients were herders based on the site. Structures and cultivation will not be permitted within the footprint once construction begins. However, only the area containing sensitive equipment will be fenced, allowing camel grazing and movement to continue across the rest of the site during construction and operation. The Project has committed to avoid and minimize impacts through layout optimization, scheduling of construction during periods of lower seasonal presence, and the use of existing access routes. The LRP has been prepared through a participatory process in line with PS5 and submitted to the Mauritanian environmental authority as part of the approved ESIA package.
Resettlement Planning and Livelihood Restoration. A cut-off date of 17 October 2025, corresponding to the drone mapping of the site, was set before the socio-economic census and asset inventory. It was communicated to affected communities and endorsed by local authorities. The physically displaced household will receive replacement housing near the Project area, suited to its family composition and provided at full replacement cost, and has been provided with a rental guarantee equivalent to three months' rent to avoid any interruption in housing while the replacement dwelling is built. No land will be taken before compensation, displacement assistance and relocation measures have been implemented. At appraisal, 23 of the 26 affected households had been compensated; compensation for the three households that could not be traced has been placed in escrow, and any future claims will be handled through the Project grievance mechanism. A dedicated specialist will oversee LRP implementation and monitoring (ESAP #3).
Livelihood restoration measures were aligned with community priorities through successive rounds of consultation. The cooperative has opted for an integrated intensive livestock operation, including the required infrastructure, starter stock, equipment, and technical and organizational support. Targeted measures will provide additional support to vulnerable households in line with PS5, over an implementation period of about 14 months. The Project will monitor livelihood restoration against pre-displacement income levels rather than the delivery of inputs alone. IWA will commission an independent, PS5-aligned completion audit to confirm that livelihoods have been restored and, where necessary, to define corrective actions to be completed before the action is closed (ESAP #8).
PS6: Biodiversity Conservation and Sustainable Management of Living Natural Resources
The Project is located in the Sahara Atlantic Coastal Desert Ecoregion. The Project area and the wider landscape are characterized by open sand and gravel plains with sparse desert shrubland, used for grazing by camels and other livestock. The western and south-western parts of the site have been modified by roads and sand mining. The Project does not overlap any legally protected or internationally recognized area; the Aftout es Saheli Key Biodiversity Area (KBA) lies about 2 km west of the Project boundary at its closest point.
Most of the Project area qualifies as Natural Habitat under PS6, with some Modified Habitat in the western part of the site near the road, where sand mining has occurred and grazing pressure is highest. The area does not meet the thresholds for Critical Habitat. Several nationally threatened species are confirmed or expected to occur and will be managed in line with regulatory requirements. An avifauna monitoring program began in spring 2026 and will continue until 2027. As PS6 requires no net loss of Natural Habitat where feasible, IWA will assess the extent of habitat loss resulting from construction and, taking into account the updated CIA, develop a no net loss strategy to be integrated into the Project Biodiversity Management Plan (BMP) (ESAP #9).
The Project site is close to an existing transmission line, and the planned interconnection line is about 350 m long. Proximity to the Aftout es Saheli KBA raises the risk of collision for migratory and soaring birds associated with the KBA and the wider East Atlantic and Mediterranean–West African flyway. Although the Project area does not contain habitats that would support the regular occurrence of these species, overflights cannot be ruled out. Collision risks will be addressed through suitable controls, such as bird flight diverters, and monitoring measures in the BMP (ESAP #9). Invasive alien species, such as Prosopis juliflora, are present in the Project area; measures to monitor and manage them will be included in the BMP (ESAP #9).