PROJECT

Projects

Environmental & Social Review Summary

Project Number

51260

Company Name

Aukera Project Company DELTA SRL

Date ESRS Disclosed

Mar 5, 2026

Country

Romania

Region

Europe

Last Updated Date

Mar 6, 2026

Environmental Category

B - Limited

Status

Pending Approval

Sector

Electric Power Other (Including Holding Companies)

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The proposed investment is an IFC loan of up to €136m in an up to €336m total debt financing for a greenfield portfolio of standalone battery energy storage systems (“BESS”) in Romania (“Project”) that is being developed by Aukera BV (“Sponsor” or “Aukera”). The Project will have an aggregate storage capacity of up to 1.9GWh for a total estimated Project cost of up to €450m. Stage I of the Project comprises two ready-to-build BESS assets in Gura Ialomitei in South-East Romania. Stage II involves three additional BESS assets spread across locations along the country’s North-East to South-East nodes in Dumbrava, Roman, and Lacu Sarat. Aukera has secured lease agreements with landowners and has obtained rights of way for grid connections, where necessary.

The works required at each of the BESS sites include site preparation and laying of foundations and internal roads, the installation of batteries and control facilities, installing the 33kV/110kV transformer substation and trenching the cable route to connect to the grid via underground cabling. Once operational, the systems will be fully automated. Construction of the first BESS asset in Stage I commenced in October 2025 and is scheduled to be completed by mid-2026, with the second asset in Stage I due for completion and start of commercial operations by the end of 2026.

Stage I has a planned capacity of 250MW (500 MWh), with a total site area of 38,700m² lying approximately 500m from the outskirts of Gura Ialomitei. For Stage II, the Dumbrava site has a planned capacity of 200MW (400MWh) and is situated in the Savinesti Commune adjacent to the Dumbrava substation on the northern edge of the village of Dumbrava-Deal, on a 27,000m² plot approximately 4km north of the town of Roznov. The Roman site (capacity 200MW / 400MWh) is located on a 50,000m² plot approximately 350m from the substation on the northern outskirts of Roman, a municipality in Neamt County, northeastern Romania. The Lacu Sarat site (capacity 300MW / 600MWh) in Braila County is on a 35,000 m² plot approximately 1.5km east of Tudor Vladimirescu Commune and 1.2km northwest of the Lacu Sarat substation.

Aukera is an emerging BESS and renewable energy developer with a footprint in Romania since 2021. The company has a ~14.6GW pipeline, with 6.5GW in projects at an advanced stage of development and 810 MW under construction across Romania, UK, Italy, and Germany.

The EPC (Engineering, Procurement, and Construction) contractor has been selected and contracted for Stage I.

Overview of IFC's Scope of Review

IFC’s Environmental and Social (E&S) appraisal comprised (i) a review of 1) corporate E&S policies and procedures made available by the Sponsor and EPC Contractor, and 2) the Environmental and Social Impact Assessment (ESIA) prepared for Stage I including an Environmental and Social Management Plan (ESMP) and Stakeholder Engagement Plan (SEP); and (ii) an in-person appraisal visit on January 28th 2026 to the BESS site at Gura Ialomitei, during which meetings were held with the Aukera, the EPC Contractor, Owner’s
Engineer (OE), and Lender’s Technical Advisors.

IFC’s E&S scope of review encompassed the Sponsor’s corporate E&S policies, and procedures and management systems and the EPC Contractor’s documents for both Project stages to the extent feasible based on the level of information available.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
20250206_ESIA Report Final_rev_clean_eng.pdf
20250206_NTS_rev_final_clean_eng.pdf
20260206_SEP_Gura Ialomitei_rev_final_clean_eng.pdf