PROJECT

Projects

Environmental & Social Review Summary

Project Number

50842

Company Name

Net Zero Energy LLC

Date ESRS Disclosed

Nov 14, 2026

Country

Mongolia

Region

East Asia and the Pacific

Last Updated Date

Nov 17, 2026

Environmental Category

B - Limited

Status

Pending Approval

Sector

Wind Power - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

The proposed IFC investment is an A loan to support the Bilgeh Wind Farm (the “Project”), a 150 MW utility-scale wind power facility. The greenfield project includes a 50 MW / 100 MWh Battery Energy Storage System (BESS) and an associated ~65 km 220 kV overhead transmission line (OHL). The Project is located in the Tsogttsetsii soum of the Umnugovi (South Gobi) region of Mongolia and is being developed by Net Zero Energy LLC (NZE or the “Company”), a special purpose vehicle that is currently 90% owned by MCS Mongolia LLC (MCSM) (with the expectation that its shares will be fully or partially transferred to MCS Energy Holding LLC (MCSE)) and 10% owned by Ureca LLC (Ureca), a local clean technology company. The Project will supply off-grid, captive power to the Oyu Tolgoi (OT) copper-gold mine under a 20-year corporate power purchase agreement (PPA).

The Project is currently in the pre-construction phase. Early works, focusing on site preparation for ancillary facilities, are scheduled to begin on November 15, 2026 under a Limited Notice to Proceed.

Main construction will commence in March 2027 and will last for approximately 17 months, targeting commercial operations in Q1 2029. The Project lease covers a 20,438-hectare area, while the total project footprint totals approximately 130.53 hectares. The temporary construction areas will comprise progressive crane pads and turbine laydown areas, temporary storage, concrete batching, a temporary solar PV and BESS for construction power, and a workers' accommodation camp sized for a peak workforce of 250–300 personnel. The permanent physical footprint includes approximately one hectare for the foundations of 24 Envision Energy ‘EN 6.25-182’ wind turbine generators (WTGs), a 5-hectare fenced area for the 220/35 kV substation and co-located 100 MWh containerized Lithium Iron Phosphate BESS, and footprint alterations from 56.1 km of unpaved internal roads and a ~29.1 km unpaved external access road (where physical clearing starts in December 2026). Power transmission to OT will be provided via a ~65 km 220 kV double-circuit overhead line (OHL) supported by 228 towers. Operations will employ approximately 34 staff, with EPC and O&M oversight managed jointly by MCS International and Envision Energy.

The Project is located in the South Gobi region of Mongolia, approximately 60 km from the Oyu Tolgoi mine and 130 km north of the international border with China. The site is characterized by a high plateau of open desert steppe, which is sparsely populated by nomadic herding communities who use the area for livestock grazing. The nearest permanent settlement is the Tsogttsetsii soum center. The Project site itself is located 26.4 km from the Galba Gobi Key Biodiversity Area (KBA) and 36.3 km from the Small Gobi A Strictly Protected Area. The ~65 km OHL route traverses one locally protected area (Gurvan Gavluud, Har Deliin Tolgod and Ih Baga Luus) for approximately 12.2 km. This area already contains existing infrastructure, and national regulations permit the construction of linear infrastructure like transmission lines within its boundaries.

Further, IFC is considering to finance other solar, wind and BESS projects to be built and operated by SPVs to be set by MCS Energy Holding (MCSE).

Overview of IFC's Scope of Review

IFC’s E&S review of the proposed Mongolia NZE investment included meetings with NZE, MCS, and Ureca management on May 12, 2025, and an in-person visit to the project site on May 14, 2025. IFC’s due diligence also included (i) a review of available E&S documentation, including the project’s Environmental and Social Impact Assessment (ESIA), (ii) discussions with ERM, the E&S consultant that prepared the ESIA, as well as ERM sub-contractors involved in social (EcoTrend) and biodiversity (Mongolica) surveys, and (iii) consultations with a sample of potentially affected households in the project area.

Further, prior to decision on financing of future MCSE project(s), IFC will complete an E&S review of those project(s) and disclose the review findings.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
01_ESIA_V05_EN_Ch0-1_Executive_Summary_and_Introduction_censored.pdf
02_ESIA_V05_EN_Ch2_Policy_Legal_Administrative_Framework_censored.pdf
03_ESIA_V05_EN_Ch3_Project_Description_censored.pdf
04_ESIA_V05_EN_Ch4_Impact_Assessment_Methodology_censored.pdf
05_ESIA_V05_EN_Ch5_Scoping_Study_censored.pdf
06_ESIA_V05_EN_Ch6_Environmental_Social_Baseline_censored.pdf
07_ESIA_V05_EN_Ch7_Environmental_Impact_Assessment_censored.pdf
08_ESIA_V05_EN_Ch8_Social_Impact_Assessment_censored.pdf
09_ESIA_V05_EN_Ch9_Unplanned_Events_censored.pdf
10_ESIA_V05_EN_Ch10_Cumulative_Impact_Assessment_censored.pdf
11_ESIA_V05_EN_Ch11_ESMP_censored.pdf
12_ESIA_V05_EN_Ch12_Stakeholder_Engagement_censored.pdf
14_ESIA_V05_EN_AnnexB_Critical_Habitat_Assessment_censored.pdf
16_ESIA_V05_EN_AnnexF_Construction_BMP_censored.pdf
17_ESIA_V05_EN_AnnexH_Livelihood_Restoration_Framework_censored.pdf
18_ESIA_V05_EN_AnnexI_Future_Stakeholder_Engagement_Log_censored.pdf
19_ESIA_V05_EN_AnnexJ_ESIA_Disclosure_Summary_censored.pdf
0747189 NZE ESIA WPF BESS_ESIA_Non-technical Summary_V3_20261102.pdf