Environmental & Social Review Summary

Project Number

50384

Company Name

OYU TOLGOI LLC

Date ESRS Disclosed

Nov 18, 2024

Country

Mongolia

Region

East Asia and the Pacific

Last Updated Date

Jan 1, 2025

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Dec 19, 2024
Signed : Dec 20, 2024
Invested : Dec 30, 2024

Sector

Copper

Industry

Metals and Mining

Department

Infra-WBG Dir. Minerals & Metals

Project Description

 The proposed investment comprises of an IFC A Loan of up to US$100 million and the possible mobilization of parallel loans from international and local commercial banks for the provision of a working capital facility (WCF) to Oyu Tolgoi LLC (“OT” or the “Company”) (“Project”). OT is an existing IFC client (under project # 29007). In December 2015, IFC provided a US$400 million A Loan, as part of the US$4.4 billion project finance facility (PFF), to support development of the Oyu Tolgoi copper and gold mine in the Southern Gobi region in Mongolia (IFC/R2013-0033).  The public disclosure documents for the previous investment are available at: https://disclosures.ifc.org/project-detail/ESRS/29007/oyu-tolgoi-llc.

 

IFC is considering a short-term facility to support OT’s working capital needs. The facility will support development of the original Project as already approved in 2015, i.e. construction and development of the OT copper-gold mine with no change in the scope of the original Project.

The OT mine is located in the South Gobi region of Mongolia, approximately 600 km south of the Ulaanbaatar, and 80 km north of the Mongolia-China border. OT currently operates open pit mining at the Southern Oyu deposit and limited production from block cave underground mining operations in the higher-grade Hugo North deposit (which is currently being developed and production rates will be increased in the coming years). Year-over-year copper concentrate production continues to increase. Construction of the underground mine involves eventual development of more than 200 km of underground tunnels at a depth of up to 1.3 km. Underground tunnelling is progressing consistently, and underground operations are expected to be fully ramped up by 2027.

The proposed facility builds on the 2015 investment and provides short-term liquidity support for OT to ensure that it continues to stay on track with its operational targets, as well as with its development contributions. This ESRS thus builds upon the previously disclosed ESRS for the original project #29007 and provides an update on the key E&S risks and impacts that are being managed as part of the previously disclosed ESAP.

Overview of IFC's Scope of Review

 IFC along with other lenders have been supervising this project since construction. An Independent Environmental and Social Consultant (IESC) performs bi-annual audits of the mine and the IESC reports are disclosed on the OT web site (https://admin.ot.mn/wp-content/uploads/IESC_Audit_Report_Oyu_Tolgoi_May_2024.pdf). The most recent available report is a draft report dated October 2024 which is based on a September 2024 monitoring visit to OT by the lenders and the IESC. This report will be finalized and likely to be disclosed by December 2024. IFC’s due diligence for this project is based on the IESC October 2024 draft report, field supervisions done by the IFC team in September 2024, and other technical documentation including various monitoring reports shared by OT.

 

IFC’s existing investment #29007 was subject of two complaints to IFC’s Compliance Advisor and Ombudsman (CAO) office which were closed in 2020 after Complaint Resolution Agreements #1 and #2 (CRAs) were reached between the complainants and the Company through a successful dispute resolution process. The review of this new investment benefited from the structures and mechanisms for stakeholder engagement as well as the CAO process, relevant information available at: https://www.cao-ombudsman.org/cases/mongolia-oyu-tolgoi-01khanbogd and https://www.cao-ombudsman.org/cases/mongolia-oyu-tolgoi-02khanbogd

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan