PROJECT

Projects

Environmental & Social Review Summary

Project Number

50309

Company Name

Abydos for Renewable Energy, SAE

Date ESRS Disclosed

May 2, 2025

Country

Egypt, Arab Republic of

Region

Africa

Last Updated Date

Jan 26, 2026

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Sep 26, 2025
Signed : Nov 24, 2025
Invested : Jan 20, 2026

Sector

Solar - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

    

The ABYDOS II project will be Egypt’s largest solar Photovoltaic (PV) power plant with a Battery Energy Storage System (BESS). The project consists of the development, construction, operation and maintenance of a 1GW solar PV power plant and 600 MWh BESS (the Project), located in Aswan Governorate, Egypt. The project will be developed on approximately 20km2 of government-owned land adjacent to Luxor-Aswan Highway. The project is being implemented by the Abydos for Renewable Energy SAE (hereafter referred to as “AFRE”), a special purpose vehicle wholly owned by AMEA Power Ltd (hereafter referred to as “AMEA” or the “Sponsor”). Established in 2016, AMEA develops, owns, and operates renewable power projects in Africa, the Middle East and Asia. The total project cost is estimated at around US$750 million. IFC is considering a i) A Loan of up to US$120 million; and ii) US$ interest rate swaps representing an expected positive exposure of up to US$15 million. In addition, IFC is expected to mobilize up to US$480 million in the form of B and Parallel loans.

The Project is also planned to comprise of i)144 Central inverter stations to convert electricity from the panels from Direct Current (DC) to Alternating Current (AC) to be connected to a substation through underground cables; ii) a substation for connection with the High Voltage National Grid (from 33kV or 22kV depending on final design to a 500kV); iii) an integrated control system and Energy Management System (EMS) for efficient BESS operation; iv) infrastructure including offices and a control building (including data, control and voice communication system); v) a warehouse; vi) a road network including internal access roads and a security perimeter road; and vii) a security fence surrounding the entire site.

During the construction phase, the Project will also include storage areas, a mobile concrete batching plant and generators. There will also be an Overhead Transmission Line (OHTL) of approximately 1.6 kilometers connecting the National Grid to the Project’s substation, which will be constructed by the Egyptian Electricity Transmission Company (EETC), who are also the offtaker and grid operator. The OHTL is considered an Associated Facility (AF) as per IFC Performance Standard.  An Addendum to the project Environmental and Social Impact Assessment (ESIA), aligned with IFC Performance Standards (PS), will be developed once EETC confirms the route of the OHTL.

 

This is a greenfield project situated in government-owned vacant desert land about 1km east of the Luxor-Aswan Highway, allocated to the New Renewable Energy Agency (NREA) in 2017, for the development of renewable energy projects. A usufruct agreement was signed between NREA and AFRE, together with a Power Purchase Agreement (PPA) for 25 years between EETC and AFRE. No human habitation, grazing, or agriculture was observed on, or adjacent to, the site. The closest communities to the project site are Al Raqaba Foaniyeh and Al Raqaba Tahtaniyeh in the Aswan Governorate, which are located approximately 6.5 kilometers away.

The construction phase is anticipated to take about 17 months. The Equipment, Procurement and Construction (EPC) Contractor has been selected and were given the notice to proceed in January 2025. At the time of the appraisal, topographical and pullout surveys were being undertaken and the project is expected to be operational by end May 2026.

 

Overview of IFC's Scope of Review

       IFC’s Environmental and Social (E&S) appraisal of the proposed project consisted of i) kick off call with AMEA and Lender’s E&S consultant on 30 January 2025; ii) reviewing technical Environmental, Social, Health, and Safety (ESHS) documentation made available by the sponsor, including the ESIA and draft E&S management plans (ESMPs); iii) accompanying the Lenders’ appointed E&S Due-Diligence (ESDD) consultant, and AMEA and AFRE project representatives to a 2-day visit on the 4th and 5th February 2025.

 

The main documents reviewed as part of the E&S appraisal included: i) the solar park ESIA;  ii) the draft Environmental and Social Management System (ESMS) manual; iii) AFRE Solar Plant Non-Technical Summary (NTS); iv) AFRE’s Rapid Cumulative Impact Assessment (RCIA); v) AFRE’s Stakeholder Engagement Plan; vi) AFRE’s policies and procedures including Environmental, Quality, Social Sustainability, Health, Safety and Gender Equality policies, Labor Code of Conduct and Supplier Code of Conduct; vii) EPCs draft ESMP; and viii) EPCs corporate policies, procedures and certificates.

 

The E&S appraisal also included meetings with the project team including AFRE’s Social Manager and Health Safety and Environment (HSE) Manager; relevant governmental authorities (Daraw city council, Aswan Labor Office, Egyptian Environmental Affairs Agency (EEAA) Environmental Office, New Aswan Waste Management Department and New Aswan Water and Wastewater Company; Benban PV solar park facilities management contractor; and Daraw based NGO (Al Noor Twesa Village).

 

The region has several contextual risks including terrorism, restrictions to civil liberties, exposure to natural disasters, gender and workplace discrimination, labor and contractor management and weak governance structures. These risks require mitigation measures as per PS1, PS2 and PS4.

 

Given AMEA is an existing IFC client, the appraisal also considered the sponsor’s Environment, Health and Safety (EHS) performance on existing investments under current IFC supervision (links to project disclosures below), where AMEAs E&S performance is currently rated as satisfactory.

                                            

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
AFRE - 1 GW Solar PV Project_SEP.pdf
Annex 2_RCIA_AFRE.pdf
AFRE - 1_GW_Solar_PV_Project_ESIA_Report_REV5.pdf