PROJECT

Projects

Environmental & Social Review Summary

Project Number

49926

Company Name

SANIFER SARLU

Date ESRS Disclosed

Jul 22, 2025

Country

Madagascar

Region

Africa

Last Updated Date

Mar 28, 2026

Environmental Category

B - Limited

Status

Pending Disbursement

Previous Events

Approved : Nov 17, 2025
Signed : Mar 25, 2026

Sector

other

Industry

other

Department

Regional Industry - MAS Africa

Project Description

 IFC’s proposed project is a US$10m corporate A-Loan (“IFC Loan”) to SANIFER SARL (“SANIFER”, or the “Borrower”) and KIBO SARLU (“KIBO” or the “Co-Borrower”) (collectively the “Companies” or the “Borrowers”). The companies form part of Groupe Talys (the “Group”), a family-owned conglomerate based in Madagascar.

SANIFER was established in 1993 and is one of the country's largest importers and distributors of construction materials and home improvement accessories. SANIFER currently operates five stores in Madagascar and trades more than 23,000 items from over 385 suppliers.

KIBO is a wholesale Fast-Moving Consumer Goods business based on the ‘Cash & Carry’ concept. Since its establishment in 2021, KIBO currently operates 3 stores in Madagascar.

The Group operates a warehouse in Antananarivo (25,000m2), which is utilized by the Borrowers.

The IFC investment will support the development of five new stores, including SANIFER Nosy Be and KIBO Nosy Be  (located on the same site), and SANIFER Ivato, KIBO Ivato, and SANIFER Bypass. Additionally, the investment will facilitate the implementation of the Sage X3 Enterprise Resource Planning (“ERP”) system for the Companies and the refinancing of the Borrowers' outstanding working capital credit facility, collectively referred to as the Project.

Overview of IFC's Scope of Review

 IFC’s appraisal, conducted in April 2025, included site visits to operational SANIFER and KIBO stores in Alarobia, central Antananarivo and SANIFER and KIBO stores currently under construction in Ivato.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan