PROJECT

Projects

Environmental & Social Review Summary

Project Number

49607

Company Name

Eurasia Group Kazakhstan LLC

Date ESRS Disclosed

Nov 14, 2025

Country

Kazakhstan

Region

Central Asia and Turkiye

Last Updated Date

Feb 7, 2026

Environmental Category

B - Limited

Status

Pending Signing

Previous Events

Approved : Feb 6, 2026

Sector

Agriculture, Construction, and Mining Machinery

Industry

Manufacturing

Department

Regional Industry MAS MCT

Project Description

The proposed IFC investment is a loan of up to US$33 million (M) to two subsidiaries of Eurasia Group AG, a Switzerland-based company (EG AG, the Guarantor), namely Eurasia Group Kazakhstan LLC (EG KZ) and Eurasia Group Kyrgyzstan LLC (EG KG). The Guarantor distributes and services John Deere and other western-made agricultural machinery through its subsidiaries in Kazakhstan and the Kyrgyz Republic. The proposed financing to EG KZ and EG KG (together, the Companies) will be for the construction of three service centers in Astana, Almaty and Pavlodar in Kazakhstan and one service center in Bishkek, Kyrgyz Republic (the Project). The four service centers will allow the companies to support local farmers and agricultural production in both countries through distribution and maintenance services of agricultural machinery.

Overview of IFC's Scope of Review

IFC’s E&S review of this proposed investment included (i) site visits to the EG KZ headquarters (HQ), the existing service center in Kokshetau, and the construction yard in Astana in July 2024; (ii) meetings with EG KZ representatives including the general manager (GM), financial director, human resources (HR) manager, administrative affairs executive, project development team, and occupational health and safety (OHS) specialist; (iii) virtual meeting with the representatives of EG KG, including GM, commercial director, HR responsible and after sales manager, who functions as OHS responsible; (iv) interviews with selected employees; and (v) review of E&S documents and information provided, including the companies` organizational structure, HR procedures, workplace measurement reports, fire safety audit reports and project related information and studies such as construction documentation.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Environmental and Social Review Summary_V1.pdf