PROJECT

Projects

Environmental & Social Review Summary

Project Number

49394

Company Name

Kazakhstan Temir Zholy

Date ESRS Disclosed

Apr 28, 2025

Country

Kazakhstan

Region

Central Asia and Turkiye

Last Updated Date

Feb 26, 2026

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Aug 4, 2025
Signed : Jan 9, 2026
Invested : Feb 13, 2026

Sector

Rail Transportation

Industry

Infrastructure

Department

CN5CT - Regional Industry INF MCT/INF Central Asia & Turkey

Project Description

The proposed IFC financing is for an A Loan of up to US$ 200 million to Kazakhstan Temir Zholy Joint Stock Company (KTZ JSC) (“KTZ” or the “Company”), national transport and logistics holding company that manages the railway infrastructure and operates freight and passenger services in the Republic of Kazakhstan (RoK). The financing is for the construction and operation of five train stations and auxiliary structures as defined below for passenger and freight railway service of the Almaty Railroad Bypass (the “Project”) which is part of the Trans-Caspian International Transport Route and the Middle Corridor.

The project is a greenfield development with brownfield station rehabilitation components, and its footprint comprises a 300 m wide Right of Way (RoW) (i.e., 150 m on either side of the line) at the train stations, a 160 m wide RoW (80 m on either side of the line) for the construction of railway sections between the stations (including construction sites) and with a 10 m railway line footprint included for the other parts of the railway line. The project will include construction and operation of (i) 75 km railway line, with a total track length of 130 km, between Kazibek Bek and Zhetygen stations, across the districts of Talgar, Ilyisky, Karasai and Zhambyl districts and Alatou city in the Almaty region; (ii) three new stations at Sorbulak, Moyinkum and Zhana Arna, and rehabilitation of Kazibek Bek and Zhetygen stations; (iii) two 500/220 kV substations connecting the project to 220 kV overhead lines supplied by the Kazakhstan Electricity Grid Operating Company (KEGOC); (iv) a 73 km single-circuit 10 kV underground line that powers auxiliary systems along the entire length of the alignment, and 1.9 km 220 kV overhead transmission line connecting the substations; (iv) auxiliary structures including 59 culverts, 13 bridges, 11 level crossings, six cattle crossings, five railway overpasses and a vehicular overpass; and (v) depots, maintenance and servicing facilities, workers accommodation and other supporting infrastructure at the stations and diversion of 18 Overhead Transmission Lines (OHTL) which are operated by KEGOC.

Large scale earthwork activities are required (6.2 million cubic meters) and there are 14 state owned quarry sites (176.6 ha in total) identified for the abstraction of soil and sand that are mostly located outside the RoW. The distances of the quarry sites from the nearest residential areas vary between 4 km and 29 km. Crushed stone supply for track ballast and pavement base is sourced from Malaysary station, approximately 120km from the construction site. Concrete for stations and depots will be prepared on site at temporary concrete batching plants and offsite for sleepers with the closest approximately 60 km from Almaty. The rail tracks will be prefabricated and supplied by local factories.

Temporary and mobile workers accommodation camps are being established by sub-contractors along the railway RoW based on the locations of ongoing construction works.

KTZ commenced construction enabling works in November 2023. The Engineering, Procurement and Construction (EPC) Contractor was appointed on March 1, 2024.  The overall construction duration is estimated to be two years. At the time of project disclosure, 40% of the construction works were complete. The new railway line is scheduled to start operating by the first quarter of 2026.

Overview of IFC's Scope of Review

IFC's environmental and social (E&S) appraisal included two site visits conducted in March 2024 and April 2024. KTZ’s headquarters in Astana, railway construction sites, quarry sites and surrounding areas, the construction assembly hub of the EPC contractor and a workshop of a subcontractor were visited during the site appraisal. Meetings were held with the managers and representatives across different departments including implementation, technical policy, investor relations, strategy and human resources (HR).  The IFC team also met with representatives of the trade union. IFC consulted with the local biodiversity related civil society organizations (CSOs) and the Inspectorate of Forestry and Wildlife of the Almaty Oblast.

IFC also undertook reviews of environmental, health and safety (EHS) and social related information submitted by KTZ including the Environmental Impact Assessment (EIA) completed in 2023, and the Supplementary Environmental and Social Impact Assessment (ESIA) including an integrated Environmental and Social Management Plan (ESMP) that was completed in April 2025, its Non-Technical Summary, Construction E&S Management System (ESMS) including integrated topic-specific and corresponding E&S management plans (ESMPs for air quality, soil & water quality, noise, community health and safety) and the Biodiversity Management Plan (BMP), the Cultural Heritage Management Framework, the Stakeholder Engagement Plan (SEP) and the Livelihood Restoration Plan (LRP) including a Resettlement Framework (RF) disclosed with this ESRS.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
CESMS ((inclusive of BMP).zip
ESIA_ESMP (inclusive of CHMF).zip
LRP_RAF.zip
SEP_GRM.zip
Almaty Bypass_Full.pdf
Almaty Bypass Supplementary NTS Compiled Final Report.pdf
Almaty Bypass Supplementary NTS Compiled Final Report_RUS_Final.pdf