PROJECT

Projects

Environmental & Social Review Summary

Project Number

49272

Company Name

Elementum Energy Limited

Date ESRS Disclosed

Mar 5, 2026

Country

Ukraine

Region

Europe

Last Updated Date

Mar 5, 2026

Environmental Category

B - Limited

Status

Pending Approval

Sector

Renewable Energy Holding Companies

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

The proposed investment is a corporate facility of up to EUR 250 million to Elementum Energy Limited (Elementum, or the company), the second largest renewable energy producer in Ukraine. Proceeds will be used for the development, construction and operation of the following subprojects in Ukraine (together referred to as the Project):

• the Danube Wind Power Plant (Danube WPP), comprising three greenfield wind power plants (WPPs), each with three wind turbine generators (WTGs), all located in southern Ukraine; and
• the Ternopil (also referred to as Windpark West-R) WPP, comprising 32 WTGs and a dedicated substation located in western Ukraine.

In addition, viability gap funding may be provided for a pilot battery energy storage system (BESS), located at one of the company’s existing facilities in southern Ukraine.

Each of the three Danube WPP subprojects is being implemented by separate, 100% Elementum owned, special purpose vehicles (SPVs), which will together have a combined installed capacity of 57.6 MW. Ternopil WPP is at an earlier stage of development than Danube WPP but will be similarly delivered through a dedicated SPV, Windpark West-R LLC.

Both Danube and Ternopil WPPs will use horizontal three blade WTGs (in 6.4 MW power mode) with a hub height of 125m and a rotor diameter of 162m, connected by newly built access roads, along which underground cabling will be routed, and link to the local public road networks. All the land required for both projects is currently used for agricultural purposes and is being secured for 49 years via a combination of voluntary lease and easement agreements concluded with private and public landowners. No physical displacement is required for either project. Residential receptors are located at sufficient distances from the proposed WTGs to comply with applicable national requirements and IFC/WBG EHS Guidelines.

Construction timelines are aligned with the project development schedule, and a 25-year operational period has been estimated for both projects.

The pilot BESS will have a capacity of 10 MW/20 MWh, with equipment comprising lithium iron phosphate storage cells assembled in five 20-ft containers, each with a capacity of 4.5 MWh situated within an existing company facility. It will be installed in the second quarter of 2026 and will operate for an estimated 15-20 years.

Elementum (https://www.elementumenergy.com/) is the second largest private renewable energy producer in Ukraine and is fully owned by VR Global Partners, L.P., an international asset manager specializing in distressed and special situations in emerging markets, with a longstanding presence in Ukraine. Elementum operates 28 solar plants with a total installed capacity of 536 MWp and one wind power plant with a capacity of 100 MW.

Overview of IFC's Scope of Review

This is a corporate investment, with defined use of proceeds which may generate environmental and social impacts. Therefore, according to the IFC E&S review procedures for such finance, the appraisal covered the company’s E&S Management System (ESMS) capacity, maturity and organizational resources to effectively manage the E&S risks of the defined use of proceeds. The initial focus was therefore on evaluating the company’s corporate policies, procedures and operational practices against the IFC Performance Standards (PS) and applicable World Bank Group General and sector specific (Wind Farm and Wind Energy) Environmental, Health, and Safety (EHS) Guidelines. Reviews were also undertaken of project specific documentation, where available, notably the Environmental Impact Assessments (EIAs) developed to fulfill national requirements and subsequent EIA gap analyses, undertaken by an international consultant, for both WPP subprojects, supplementary biodiversity studies at the Danube WPP site undertaken in late 2025 to meet IFC requirements, and the company’s responses to a series of E&S questionnaires submitted by IFC’s Independent Environmental and Social Consultant (IESC). The appraisal also included regular discussions between IFC, the IESC and company representatives responsible for E&S performance and project delivery, between July and October 2025.

A physical site visit was undertaken in August 2025 by local E&S consultants, under the direction of the IESC, Elementum’s operational facilities (all solar photovoltaic plants), as well as to the operating wind power plant and the locations of the three proposed wind power plants forming the Danube WPP. Due to Russia’s ongoing invasion of Ukraine and related risks, IFC faces limitations in undertaking visits to subproject sites, however visits to the Danube and Ternopil WPP sites were undertaken respectively by local consultants under the direction of the IESC, and by an E&S specialist of one of the potential co-lenders. In addition, due to the invasion, it may also take longer for the company operations to align with the Performance Standards than in other contexts. After these constraints are removed, IFC will carry out relevant client supervision activities and site visits to supplement its E&S due diligence and to support the company on a course of action, toward alignment with the PS, as needed. Information withheld due to the above-mentioned restrictions will be disclosed upon the lifting of martial law.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan