Environmental & Social Review Summary

Project Number

49109

Company Name

Candi Solar AG

Date ESRS Disclosed

Dec 17, 2024

Country

World Region

Region

Global

Last Updated Date

Apr 10, 2026

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : May 22, 2025
Signed : Nov 19, 2025
Invested : Apr 6, 2026

Sector

Solar - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

Candi Solar (Candi or the “Company”) is a dedicated solar installer, financier and operator in India and South Africa, headquartered in Switzerland. Candi started operations from India in January 2018 and began South Africa operations 18 months later. Candi offers its Commercial & Industrial (C&I) customers a zero upfront and maintenance cost rooftop solar photovoltaic (PV) solution with a wide range of products to provide solar solutions as per needs of the customers. The various products/models include power purchase agreements, instalment sales, and loans, with terms ranging from 3 years to over 20 years and systems from 100KWp to over 5 MWp. As of November 2024, its project portfolio stood at 118MWp, of which 80 MWp are operational, 34 MWp are in construction and 4 MWp have been contracted. The current split of the Company’s portfolio between India and South Africa is c. 75:25 with a target split of 50:50.

Candi is seeking to raise funding to meet its two-year capital expenditure (CAPEX) plan to increase its solar and battery PV portfolio by c.150MWp in India and South Africa (the Project). The Project Cost is US$100m with proposed investment being a secured debt financing package of US$65m - consisting of an (a) IFC A Loan of US$40m; (b) a US$10m subordinated loan from the Clean Technology Fund; and (c) US$5m subordinated Loan from a Canadian fund; and (d) a MCPP Loan of US$10m). The remaining US$35m will be provided through shareholders’ equity, to fund the CAPEX plan.

For the proposed investment, an IFC borrower entity will be created in India and South Africa i.e. Candi Solar Asset Hld PTY Limited (“IFC SA AssetCo” or “SA Borrower”) and Candi Solar IN 3 PVT Limited (“IFC IN AssetCo” or “IN Borrower”), together referred as the Borrowers.” IFC proceeds will be used in developing new asset portfolios based on the Candi’s pipeline. Most potential projects in the immediate pipeline are less than 5 MW except for four projects in India with capacities between 5 and 15 MW. In a few cases in South Africa, Candi also may finance diesel generator sets (to support clients during power cuts), which are operated by the clients themselves. These may only account for 2% of the planned use of proceeds.

Overview of IFC's Scope of Review

Considering the nature of the investment and operations, the review focussed on Candi’s E&S policies, procedures and management systems and their implementation in India and South Africa. The key documents reviewed for the project included: Candi’s ESG policies, E&S management system, contractor management policies and procedures, human resources (HR) policies and supply chain related information.

IFC’s E&S review included site visits to a sample of sub-projects in India and South Africa in March 2024, i.e.:

  • Two operational and one under installation projects in Haryana, India (on 18th-19th March 2024); and
  • Three operational and one under installation projects in Johannesburg, Pretoria and Riverside, South Africa (on 26th-27th March 2024).

Additionally, discussions were held with heads and technical staff of various departments including environment, social, and governance (ESG), human resources (HR), project development and asset management. During the visits in India and South Africa, discussions were undertaken with contractors and their workers.

IFC’s E&S review also benefited from an E&S due diligence (ESDD) (of February 2024) conducted by an independent E&S consultant with respect to IFC PSs for a potential investor. The ESDD report and action plan covered operations in India and South Africa.     

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan