PROJECT

Projects

Environmental & Social Review Summary

Project Number

48547

Company Name

CrossBoundary Energy Access Platform

Date ESRS Disclosed

May 27, 2025

Country

Africa Region

Region

Africa

Last Updated Date

Aug 9, 2025

Environmental Category

B - Limited

Status

Pending Signing

Previous Events

Approved : Aug 8, 2025

Sector

Renewable through Financial Intermediaries - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

    IFC is proposing to make an equity investment of US$7.5 million in Preference B Shares in the CrossBoundary Access (“Access” or the “Platform”) for its 2024-2026 capital expenditure (capex) plan. This will be accompanied by an equivalent amount of US$7.5 million of concessional equity from Blended Finance in the same share class.

Access is a platform using infrastructure project finance principles to build a distributed utility by constructing and acquiring portfolios of bankable and shovel-ready, networked and distributed renewable technologies, consisting of solar hybrid mini-grids (MGs) and other adjacent technologies (i.e. battery swapping hubs, mesh grids, other) in partnership with leading developers across Sub-Saharan Africa. The objective of the Platform is to create a distributed utility at scale for off-grid rural households and businesses.

Access will use IFC’s funds to (i) support its capex plan, in line with the planned construction schedules of assets and agreements signed with the selected development partners (“Developers”); (ii) build and acquire new projects in line with the company’s mandate.

The proposed MGs have similar layouts and involve the installation and operation of ground-mounted solar modules with a capacity of 50-450 kWp (but future pipeline sites may be larger) and associated components (battery energy storage system (BESS), inverters, cables, hubs, energy management systems and diesel generator systems used for backup during low solar generation days). Project sites are selected on greenfield land, on the outskirts of target communities’ settlements, and typically span 1 to 2 acres. Electricity is delivered via low voltage lines to customers located tens to hundreds of meters away; medium voltage may be used for larger sites or for customer groups located further away from the generation unit. The battery hubs target off-grid low-income villages and consist of standalone solar system of 5-10 kW per hub powering 300 batteries of [45Wh] each available for daily rentals to customers in the community.

Access’ existing assets include project development and construction agreements with a Developer for a first batch of (15) projects in Nigeria, of which 5 are already operational, while the remaining 10 are under commissioning. Access is considering additional near-term pipeline development agreements, which involve several MG projects in collaboration with a MG Developer in Nigeria to serve approximately 20,000 connections, and battery swapping hubs (“Power Hubs”) to serve around 60,000 consumers. Further opportunities are under consideration with developers in Madagascar, the Democratic Republic of Congo, Zambia and other African countries. Developers may also construct (via Engineering Procurement and Construction (EPC) contract if necessary) and operate the projects under contract with Access.                                               

Overview of IFC's Scope of Review

 IFC's appraisal of this investment took place from June to September 2024. The process involved discussions with Access’ senior management at the company's head office in Kenya, document review and virtual meetings with representatives from the MG Developer and the Power Hubs Operator for whom development and construction agreements have been signed. IFC’s technical team also visited operating assets in Nigeria. The document review covered material shared by Access and by Developers, including IFC’s E&S questionnaire completed by Access, E&S Management System (ESMS) Manual and guidance tools, solar modules supply chain management procedures, human resources (HR) procedures, Technical Standards Books, Code of Ethics, among others. Developers’ documents reviewed included ESMS manuals where available, E&S impact assessments (ESIAs) for short-term pipeline projects in Nigeria, health and safety manuals, Developers’ E&S Action Plans (ESAP), and E&S plans such as stakeholder engagement plans (SEPs), security management plans, health and safety management procedures and reports, emergency preparedness and response plans (EPRPs), waste management plans, HR policies, and grievance mechanism.

                                             

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
ESIA Final Report EEAN.pdf