PROJECT

Projects

Environmental & Social Review Summary

Project Number

45205

Company Name

ENERSOK FE LLC

Date ESRS Disclosed

Oct 14, 2022

Country

Uzbekistan

Region

Central Asia and Turkiye

Last Updated Date

Jul 14, 2023

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Mar 9, 2023
Signed : Mar 16, 2023
Invested : Jul 11, 2023

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry INF MCT

Project Description

The proposed IFC investment is up to US$70mn A-loan and an interest rate swap to cover up to US$200mn aggregate loan notional for the IFC A Loan and ECA-covered commercial loans in order to finance the construction of a 1,600 MW greenfield combined cycle gas turbine (“CCGT”) IPP project in the Syrdarya region of Uzbekistan (“Syrdarya CCGT Project” or the “Project”). The overall cost of the project is currently estimated at approximately US$950mn. Additional financing is being provided by JBIC and NEXI. The project was awarded through competitive tendering process (supported by IFC advisory) to the consortium of EDF (331/3%), Nebras (331/3%), Sojitz (19%) and Kyuden (141/3%) (collectively the “Sponsors”) in December 2021.

The project is located in the Boyovut district, approximately 2 km northeast of the city of Shirin, in the Syrdarya region of Uzbekistan, approximately 150 km south of Tashkent. The project site is adjacent to the Syrdarya 1 IPP (currently under construction) and approximately 1.5km North of an existing gas fired thermal power plant established in 1970’s and hereinafter referred to as the Syrdarya TPP.

The sponsors have established a special purpose vehicle called ENERSOK LLC (Project Company) to deliver the project and have entered into a 25-year Power Purchase Agreement (PPA) with JSC ‘National Electric Grid of Uzbekistan’ (NEGU), who will be the off-taker of the generated electricity.

In accordance with the requirements of the PPA, construction will start in 2023 and the first gas turbine will start operating in simple cycle from February 2025. The plant will be fully operational with two gas turbines and one steam turbine in combined cycle configuration starting from February 2026.

ENERSOK has selected an EPC contractor (Harbin Electric International Company Limited) to deliver the engineering design of the facility, procure all equipment and build all temporary and permanent facilities of the project. The EPC contractor was selected through a competitive tender process from five international EPC Contractors considering financial, technical and E&S qualifications.

The main project facilities will include:

• Power block and stacks including two Gas Turbines (GT), two Heat Recovery Steam Generators (HRSG) and one Steam Turbine (ST);

• Closed Loop Cooling Water system, with mechanical draft air cooling tower blocks;Gas receiving terminal;

• Access road

• Intake and outfall corridor to a surface water canal, known as the YG Canal;

• Raw water treatment plant;

• Wastewater treatment plants (industrial and sanitary);

• Ancillary/support facilities (i.e. electrical system, site entrance and security building)

• 500/220kv switchgear station shared with and being constructed by the adjacent ACWA Power Sirdarya 1,500MW CCGT Power Plant.

The access road will be parallel to the project intake/outfall corridor to YG canal. In addition, one of the drainage ditches to the south of the project site will require modification/rerouting works to ensure its functionality and to avoid potential flooding in the area during storm events. This will be undertaken by the EPC contractor as part of the project.

Associated Facilities (AFs) will be limited to the following:

 

• 1 km gas pipeline connection to an existing gas supply system to be constructed by  NEGU (or its appointed contractor) and operated by the gas supplier, JSC Uztransgaz.

• Re-routing of an existing 500kV Overhead Transmission Line (OHTL) by NEGU before mid-2023. The OHTL currently runs through the centre of the project site and will be rerouted alongside its western boundary.                                                   

Overview of IFC's Scope of Review

IFC’s appraisal included reviewing readily available project information, which includes the national EIA and the international ESIA, including associated studies and available ESMS documentation, prepared by 5 Capitals Environmental and Management Consulting and Juru Energy Consulting LLC on behalf of the project sponsors.  The sponsor and EPC contractors’ capacity to manage the E&S risks of the project was also assessed through discussions and document reviews. The IFC team jointly with Earth Active (Independent E&S Advisor) and parallel lenders (JBIC and NEXI) participated in a site appraisal visit between 29-31 August 2022, organized by Sojitz on behalf of sponsor. This site visit program included meetings and discussions with key project staff, regulators, and local stakeholders                                                   

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Syrdarya CCGT_ESIA Vol 1 NTS_v1.2_uzbek version.pdf
Syrdarya CCGT_ESIA Volume 1 NTS_v1.2.pdf
Syrdarya CCGT_ESIA Volume 2_v1.3.pdf
Syrdarya CCGT_ESIA Volume 3_v1.2.pdf
Syrdarya CCGT_LALRP Exec Summary_v.1.0.pdf
Syrdarya CCGT_Land Acquisition and Livelihoods Restoration Plan_v.1.3.pdf
Syrdarya CCGT_Stakeholder Engagement Plan_v1.3.pdf
Syrdarya CCGT_ESIA Volume 4_v1.1.pdf