45140
CONTINUUM ENERGY LEVANTER PTE. LTD.
Feb 18, 2021
India
South Asia
Jan 26, 2025
B - Limited
Completed
Approved : Jan 28, 2021
Signed : Jan 29, 2021
Invested : Feb 9, 2021
Wind Power - Renewable Energy Generation
Infrastructure
Regional Industry - INF Asia & Pac
The project involves two operating wind farms with a combined capacity of 170 MW at Daloda and Piploda taluka in Mandsaur and Ratlam district of Madhya Pradesh, India (the “project”) set up by two Special Purpose Vehicles (SPVs) namely DJ Energy Private Ltd (“DJEPL”) and Uttar Urja Projects Private Limited (“UUPPL”). DJEPL and UUPPL are wholly owned subsidiaries of Continuum Green Energy (India) Private Limited (“CGEIPL”) (formerly known as Continuum Wind Energy (India) Private Limited (“CWEIPL”) and Surajbari Windfarm Development Pvt Ltd (“SWDPL”)) and which has a current portfolio of 757.4 MW of operational assets and 278 MW under construction assets
The project involves operation and maintenance of 85 wind turbines, with a unit generating capacity of 2 MW supplied by Inox Wind Limited (Inox). Inox was also responsible for turbine erection and commissioning and is currently responsible for turbine operation & maintenance (“O&M”). The responsibility for project development activities including land acquisition and project approvals, internal/access roads, SCADA building, turbine foundations, evacuation infrastructure, external & internal transmission lines and civil works lied with the companies. The entire project (170 MW) was commissioned in December 2015 and the construction phase lasted for 12 months (January 2015 to December 2015).
Transformers are located near the turbine within an access-controlled area and are connected to the overhead conductor at 33 kV which in turn connects to the transformer at the pooling substation. The pooling station (200 MVA, 33/220 kV capacity) is located at Bhatkheda and the turbines are located within a 20-25 km radius of the pooling substation. The pooling station is connected to the project site/turbines through six single/double-circuit feeder lines of 33 KV each with a carrying capacity of around 30MW or suitable combination. Power from the pooling station is evacuated through a 20 km 220KV double circuit transmission line to the existing substation at Daloda (33/220 kV capacity). The pooling station along with the 20 km transmission line is shared by the two companies as per government approval. The transmission line along with other associated facilities at the substation has been handed over to Madhya Pradesh Power Transmission Company Limited (MPPPTCL) after construction.
The project sites are located over revenue land of twenty villages of Piploda and Dalauda taluka in the Ratlam and Mandsaur districts. Each turbine and associated transformer is located in a land plot of approximately 1.75 hectares (ha). The total land area occupied by the project is around 230 hectares (including 151 hectares of revenue land for the wind turbines (owned by the government) and about 79 ha of private land mainly for the access roads and right of way for transmission line) and the companies have received land use permission/possession rights for a period of 25 years.
The companies currently have 25 employees on its roll at the site and 147 employees of the contractor for looking after O&M operations. The project site is located around 35 km away from another 100 MW operating wind farm of Orange Renewables.
IFC’s E&S review of the project (two contiguous operating wind farms with a combined capacity of 170 MW) consisted of a virtual appraisal in January 2021 to update the company information related to technical, EHS and social matters and included discussions with senior management of the company including representatives from the corporate EHS and HR teams. The virtual appraisal for the proposed investment built upon the information collected during the site supervision visits in December 2014 and October 2017, the review of the Annual Monitoring Reports (AMR) submitted by the company on an annual basis and responses to IFC’s E&S questionnaire. This review summary is prepared as a supplement to the Environmental and Social Review Summary for the previous investment (Project #34565: DJEPL and UUPL) published in March 2014 available at: https://disclosures.ifc.org/#/projectDetail/ESRS/34565.
IFC first appraised the project in 2014 and which included detailed review of technical, environmental and social information made available by the companies including a) the Environment and Social Impact Assessment Study (ESIA) report dated February 2014 prepared by Senes Consultants India Pvt. Ltd; b) Standard Operating Procedures for under-construction and operating assets of Inox Renewable’s Ltd (IRL and existing client of IFC #31834) to be applied to sister companies (like Inox Wind Limited); and c) Human Resource (HR) policies and procedures as applied to under-construction and operating assets. The appraisal involved site visits to the then proposed wind turbine generator (turbine) location sites and pooling substation and transmission lines being developed for the evacuation of power from the two windfarms. The review also included discussions with key corporate and site level team/staff, local community representatives, land/revenue officials and a site visit to an operating project site located in the state of Maharashtra, India.