Environmental & Social Review Summary

Project Number

42138

Company Name

KLABIN S A

Date ESRS Disclosed

Aug 28, 2019

Country

Brazil

Region

Latin America and the Caribbean

Last Updated Date

Jun 12, 2021

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Sep 27, 2019
Signed : Oct 31, 2019
Invested : May 20, 2020

Sector

Pulp Mills

Industry

Agribusiness and Forestry

Department

Regional Industry MAS LAC & EUR

Project Description

Klabin S.A. (“the company” or “Klabin”), is an integrated Brazilian pulp and paper producer, exporter and recycler in Brazil (https://www.klabin.com.br/en/). The company has 17 industrial units in Brazil, one in Argentina, and three forest management units located in Parana, Santa Catarina and Sao Paulo.

In 2013, IFC provided financing for the construction of the Puma I industrial unit located in the municipality of Ortigueira, Parana (https://goo.gl/maps/TdG4Hwoa7GYxUNHX7). Puma I started operations in 2016 and has an approximate production capacity of 1.6 million tons of bleached wood pulp per year. The public disclosure documents for this investment, are available at: https://disclosures.ifc.org/#/projectDetail/ESRS/31903.

The proposed IFC investment consists of an A/B/MCPP loan financing package to Klabin, of up to USD390 million. The proposed investment is composed of an up to USD120 million A Loan, up to USD220 million B Loan, and up to USD50 million MCPP. The proceeds will be used to fund the expansion of the Company’s kraftliner capacity. 

The project will be divided into two phases, with the construction of each phase projected to last 24 months. The first phase consists of the construction of a fiber line to produce unbleached pulp integrated with a kraftliner paper machine with annual capacity of 450,000 tons.

The second phase consists of the construction of a second fiber line integrated with akraftliner paper machine with annual capacity of 470,000 tons.

Puma I and II will run as a single production unit, with common management, maintenance and operations and the proposed project therefore will include the expansion of supporting infrastructure and utilities such as waste and wastewater treatment systems.

Raw material will originate from FSC-certified existing and new eucalyptus and pine planted forests to be developed and managed by Monte Alegre Forest Unit as well as from third-parties. The Monte Alegre Forest Unit has 361,000 hectares: 200,000 hectares are dedicated to eucalyptus and pine plantations, and 161,000 hectares are protected native vegetation. Any additional land required for the expansion of forest plantations will be acquired only through willing buyer-willing seller transactions and plantations will be implemented in fallow, silviculture or agricultural land.

Overview of IFC's Scope of Review

The E&S review of the proposed investment included a site visit in June 2019 to the existing Puma I facilities including log yard, wood handling lines, digesters, control rooms, wastewater treatment plant, waste segregation site, and waste treatment facility. The visit included presentations by and interviews with operational, environmental, health and safety (EHS), forestry, logistics, social and human resources personnel, and a visit to the indigenous community of Tibagi / Mococain the vicinity of the project. The appraisal also included the review of the Environmental Impact Assessment (RAP, for its acronym in Portuguese), Klabin's Environmental and Social (E&S) Management Program, biannual E&S compliance reports (ESCR) submitted by Klabin as part of its lenders' reporting requirements for Puma I project, biannual E&S monitoring reports produced by the Independent E&S Consultant (IESC) during the construction and operation of Puma I, and the E&S due diligence (ESDD) report for Puma II project produced by the IESC, in coordination with IDB-Invest, that included Puma industrial unit and an assessment of practices in owned and third-party forest plantations, conducted.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Relatorio Ambiental Preliminar.pdf