PROJECT

Projects

Environmental & Social Review Summary

Project Number

41216

Company Name

ELECTRIC NETWORKS OF ARMENIA CJSC

Date ESRS Disclosed

Aug 28, 2020

Country

Armenia

Region

Europe

Last Updated Date

Jun 12, 2021

Environmental Category

B - Limited

Status

Active

Previous Events

Approved : Dec 10, 2020
Signed : Dec 23, 2020
Invested : Feb 4, 2021

Sector

Distribution Business

Industry

Infrastructure

Department

Regional Industry - INF ECA

Project Description

 Electricity Networks of Armenia (ENA) is a closed joint stock company established under the laws of Armenia, which is involved in electricity transmission and distribution in the country.

 

ENA is the only electricity distributor in the Republic of Armenia (RA) with an electricity grid that spans approximately 36,000 km and one million end-users. As such, ENA operates throughout the entire country, having operational units serving all the communities of the country.

 

ENA is seeking IFC’s financial support to undertake a large-scale investment programme (the “Project”). The main objectives of this programme are to improve efficiency of operations, reduce technical and commercial losses (with corresponding carbon emissions reductions) and improve the quality of service. It involves the refurbishment of substations, updating of equipment including the vehicle fleet and meters, the reconstruction of several transmission lines, including a 110-kV line, expansion of the network by (re)-construction of low voltage lines and new subscribers connection works.

 

The Project entails financing 2020-2021 capital expenditures of ENA, which form part of the 2017-2027 investment and modernization program (US$725mn), approved by the Regulator. IFC Investment is expected to be a secured senior of US$60mn equivalent loan to be used primarily for the replacement of the distribution network equipment and refurbishment of the transmission lines.

 

In 2017 ENA received a loan from the EBRD and ADB for Phase 1. The lenders engaged an Independent Environmental & Social Consultant (IESC) to undertake an environmental, technical and financial due diligence of the company and the Project. The ESDD concluded that the investment plan does not require any resettlement or compensation, and none of the sub-projects are located in protected areas. The project has been categorized as B with corresponding ESAP agreed as the condition of the loans.      

Overview of IFC's Scope of Review

 During 2018 the IFC conducted an E&S Due Diligence (ESDD) of the company and Phase 1 of the Project (subsequently not funded by the IFC but receiving financing from EBRD & ADB) which comprised of a site visit and a series of interviews with key personal. IFC’s E&S specialist interviewed the following individuals during the ESDD: E&S staff, including Deputy Technical Director; Head of ISO Implementation Department; Head of Technical, Fire Safety, Operation, Reliability and Ecology Department; Environmental Specialist; Head of Trade Union; ENA’s E&S Advisor, Management Mix; and a sample of ENA’s employees working at the branch offices and visited Substations.

 

As a result of the travel restrictions arising from the COVID-19 pandemic, a subsequent site visit was not conducted in 2020 focusing on Phase 2 of the Project. As such, an appraisal of the company and the project was conducted April 2020, through a desktop and virtual appraisal (conducted via a series of video / phone conferences) and comprised a review of the below listed documents.

Key documents reviewed during ESDD were:

 

-          Phase 1 ESAP;

-          E&S DD reports by IESC conducted in 2017 and 2019;

-          Semi-annual Monitoring reports prepared by IESC;

-          ENA’s internal policies and procedures.

IFC’s appraisal focused on the company’s progress to complete the Phase 1 ESAP & their capacity to manage ESHS risks and compliance with the Armenian regulatory requirements and IFC’s Performance Standards and WBG’s EHS Guidelines.  Specific items addressed within the appraisal included: (i) HR policies and procedures especially on working conditions, terms of employment; (ii) occupational health and safety particularly related to electrical safety; (iii) pollution prevention with a particular focus on polychlorinated biphenyls management and potential historical contaminated sites; (iv) community health and safety and security; (v) legacy resettlement issues; (vi) biodiversity management; (vii) stakeholders engagement.   

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan