PROJECT

Projects

Environmental & Social Review Summary

Project Number

41172

Company Name

ASONHA ENERGIE SA

Date ESRS Disclosed

Aug 18, 2020

Country

Gabon

Region

Africa

Last Updated Date

Jul 28, 2022

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Jun 17, 2021
Signed : Jul 2, 2021
Invested : Jul 25, 2022

Sector

Large Hydro - Renewable Energy Generation

Industry

Infrastructure

Department

Regional Industry - INF Africa

Project Description

 The Kinguélé Aval hydroelectric power plant (the “Project”) is a proposed run-of-river 34.5 MW hydropower project which will have an average annual power production of 200 GWh.  It will be located on the River Mbé, in the northwest of Gabon, about 90 km east of Libreville. The Project will utilize the steep gradient of the Kinguélé Falls, which comprise about 20 rapids of 1-5 m height to provide the hydro-energy potential.  The concrete dam will be 48 m in height with a crest length of 470 m.  The reservoir capacity will be 4.2 Mm3, with a surface area at maximum water level of 267 ha, and the length of the lake will be about 7km. Since the project is located downstream of the two existing hydropower schemes it will only require the construction of a 300-m powerline to connect to the existing 225 kV TL, less than 1-km of new access roads, and realignment 1.4 km of the existing access road to route it around the new reservoir upstream of the dam.  Construction materials for the Project will be provided from nearby existing quarries and no new borrow pits for the construction are envisaged. The construction of the Project is forecast to take 40-45 months.  The number of workers required will vary during construction but the peak number of workers is expected to be between 450 and 700.  The staff levels during operation are not yet known but expected to be much lower than during construction.

Gabon’s energy sector has a dependence on fuel imports for thermal power plants, and the potential for hydropower has been under-exploited.  There is an urgent need to upgrade power generation to meet the growing demand, avoid more frequent power cuts, and enhance energy security.  The proposed Project will increase the installed power generation in Gabon, respond to the growing energy demand in the country, and decrease the share of electricity generated from hydrocarbons, in line with the Government of Gabon's Emerging Gabon Strategic Plan.  Construction is scheduled to start in Q4 of 2020, with commissioning planned for 2024.

The developer, Asonha Energie, is a special purpose vehicle (SPV) created for the development of the Project and incorporated under the laws of Gabon.  The SPV is owned by a consortium of Meridiam SAS (60%) and the Gabon Power Company (40%).  Meridiam is an independent international company based in Paris, France, which specializes in investment in infrastructure projects.  The Gabon Power Company is owned by the Gabonese Fund for Strategic Investments (FGIS), a sovereign fund set up in 2012 to invest in projects that would diversify from the oil and gas sector.  The power generated by the Project will be purchased by the Republic of Gabon through a Power Purchase Agreement (PPA).            

Overview of IFC's Scope of Review

 IFC environmental and social specialists have reviewed the Environmental and Social Impact Assessment (ESIA) report and complementary studies that have prepared from 2017 to mid-2020 for the construction, commissioning and operation phases of the project, and held multiple call with project sponsors, consultants and other Lenders to review a series of interim and protracted studies and reports, that resulted in the final ESIA, related studies and Environmental and Social Action Plan (ESAP) disclosed together with this ESRS.

Due Diligence was carried out by a multidisciplinary team composed of environmental, social and biodiversity professionals for a period of one year from July 2019 until June 2020, and the coverage included, among others: hydrology, geology, sedimentation, climate change impacts, review of concept design including costs, review of Project agreements and institutional aspects – with multiple site visits (in July 2019, December 2019 and February 2020) to the project site and ancillary facilities. Furthermore, Mott McDonald was hired as independent environmental and social consultants to support Lender’s group with its own due diligence. Mott McDonald undertook the site visit on 8-11 July 2019.   

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
8210771_PAB_Kinguelé aval_draft_rev4B_IFC_disclosure_20200813.pdf
c RAPPORT_COLLECTE_DONNEES_Pygmées_V7_28032020_with_Appendixes.pdf
PEPP_Kinguele_April 2020 (1).pdf
PRME_Kinguele_March 2020.pdf
8210771_EIES_PGES_Kinguelé aval_Final_Bailleurs_rev3v1 (1).pdf
8210771_EIES_PGES_Kinguel_aval_Final_rev2v3.pdf
20200617 Transmittal IFC lettre early disclosure.pdf