PROJECT

Projects

Environmental & Social Review Summary

Project Number

39879

Company Name

PT MEDCO RATCH POWER RIAU

Date ESRS Disclosed

Jul 24, 2018

Country

Indonesia

Region

East Asia and the Pacific

Last Updated Date

Jun 12, 2021

Environmental Category

A - Significant

Status

Active

Previous Events

Approved : Feb 15, 2019
Signed : Mar 20, 2019
Invested : Nov 13, 2019

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

IFC is considering providing an A loan to part finance the Riau Independent Power Producer (IPP). Riau IPP is a greenfield 275 MW gas-fired combined cycle gas turbine (CCGT) power project in Riau, Sumatra in Indonesia and a gas pipeline, water intake and discharge line, cooling towers for closed cooling system, switchyard, access road for the power plant and transmission line. (“the project”). The project will be a load following power plant with an expected annual generation of 1445 Gigawatt hours (GWh). The project sponsors, PT Medco Power Indonesia (“MPI”), an existing IFC client and Thailand’s Ratchaburi Electricity Generating Holding Company (“RATCH”) have jointly set up a company PT Medco Ratch Power Riau (“MRPR” or “the company”) to build, own and operate the plant. PT Perusahaan Listrik Negara (Persero) (“PLN”), Indonesia’s national electricity utility, will be the offtaker for the electricity generated by the project. The power plant is to be constructed by a Korean engineering, procurement and construction (EPC) company and the gas pipeline by an Indonesian contractor. The construction period for the power plant is expected to be 30 months and for the gas pipeline 12 months.

Medco Power Indonesia (“MPI”) is a developer of small to medium size IPP projects. MPI owns and operates 4 gas fired power plants with total capacity of 194 MW, is invested in a geothermal power project of 330MW and provides operation and maintenance (“O&M”) service to PLN’s 1,320MW Tanjung Jati coal power plant. MPI is a subsidiary of Medco Energi Internasional.

Ratchaburi Electricity Generating Holding Public Limited (“RATCH”) is an IPP in Thailand with total generation capacity of 6,600 MW in operation and 952 MW under development/ construction of which more than 5000 MW is gas based generation.

The project site is located in the Tenayan Industrial Village (formerly known as Sail Village), Tenayan Sub district, Pekanbaru City, Province of Riau. The project site is located approximately: 10 km east of the city of Pekanbaru in Central Sumatra, Indonesia; 3 km south of the Siak River; and 2 km south of PLN’s existing 2 x 110 MW Tenayan Coal Fired Power Station (CFPP). The main power plant is situated on a plot measuring 9.1 ha that is currently used as an oil palm plantation and which includes 1.5 ha for switchyard and 3.7 ha for the lay down area. 14. 6 ha of land is required offsite for gas pipeline, transmission line towers and right of way, temporary jetty, access road, water intake structure and pipeline, and wastewater discharge pipeline. The site is bounded by palm oil plantations to the West, South and East and Road 45 on the North. A 500 m long access road will be constructed to connect the project site with the existing road 45. The distance from the proposed power plant site to the nearest settlement of Bencah Lesung residential settlement is approximately 3 km and the distance to the Tuah Negeri settlement is about 5 km. The 40 km gas pipeline route mainly follows along the easement of existing roadways although it does at points intersect several roads, two rivers and a small creek. Approximately 10 km of the route passes through palm oil plantation land.

The main plant will comprise a combination of gas turbine (2x 81 MW), two heat recovery steam generators (HRSG) and one steam turbine and generator (1x126 MW), in a combined cycle configuration. The gas turbine and HRSG will both have dry low NOx (DLN) combustors. The gas turbine and the HRSGs will be installed in the open and the steam turbine generator will be housed within a turbine building. Two stacks of 45 m height each are proposed. Natural gas for the power plant will be supplied by PLN in accordance with Power Purchase Agreement from the existing gas connection point in TGI Gas Pipeline. The gas will be supplied through a dedicated 12inch high-pressure buried pipeline, approximately 40 km in length from the
offtake point to the project site. The gas offtake will be from the existing main Grissik to Duri pipeline at SV1401 located in the Siak Regency. The power generated by the project will be evacuated to PLN’s existing150 kV Tenayan – Pasir Putih transmission live via a new 750 m long 150 kV transmission line that will be connected to the existing transmission line. Other significant components of the project include raw water intake structure on the Siak river, up to 5 km long water intake and wastewater outfall pipelines of 200 mm and 100 mm diameter respectively, cooling towers, switch gear, emergency and black start diesel generating (DG) sets, water treatment plant (including demineralization (DM) processes), effluent treatment plant (neutralization), sewage treatment plant, fire prevention, detection, control and fighting systems, water storage tanks including for firefighting system, tanks for liquid fuel storage for the black start and emergency diesel generator sets (the gas turbines burn gas only), stores and hazardous materials storage facilities and temporary jetty on Siak river to receive equipment and construction material transported via the river for onward road transport to the project site.

Overview of IFC's Scope of Review

IFC’s review consisted of appraising technical, environmental and social information related to the Riau IPP project submitted by MRPR including: Environmental and Social Impact assessment (ESIA) report dated July 2018; MPI and MRPR Human Resource Policy Handbook; Lenders’ E&S Advisors’ review report; and project EPC contract.

The review included a visit to the Riau IPP project site and proposed gas pipeline route in 11-12 December 2018. The visits included discussions with the company’s project, technical management and environment and social professionals, and consultation with a sample of members from the affected communities at the project site and along the gas pipeline route. In this review, IFC has also drawn upon the information and experience from its existing investment in MPI (# 31462), which is implementing an action plan, which upon implementation will make its E&S performance is satisfactory.

IFC’s appraisal considered outline of the environmental and social management plans for Riau IPP project, and gaps, if any between these plans and IFC requirements. Where necessary, corrective measures, intended to close these gaps within a reasonable period of time, have been outlined in the agreed Environmental and Social Action Plan (ESAP) disclosed in this environment and social review summary (ESRS). Through implementation of these management plans and the ESAP, Riau IPP is expected to be operated in accordance with the IFC Performance Standards (PS) objectives.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
LRF Entitlement Matrix Updated.pdf
AM039100_Riau ESIA - Volume 4_Framework ESMS and ESMP_V3_Final Draft for July Disclosure.pdf
AM039100_Riau ESIA - Volume 3_SIA_V3_Final Draft for July Disclosure.pdf
AM039100_Riau ESIA - Volume 2_EIA_V4_Final Draft for July Disclosure.pdf
AM039100_Riau ESIA - Volume 1_Introduction_V5_Final Draft for July Disclsoure.pdf
AM039100_Riau ESIA - Volume 5 Technical Appendices_V3_Final Draft for July Disclosure.pdf
Draft Biodiversity Action Plan.pdf
MRPR_Supplementary Information on Indigenous Peoples.pdf