PROJECT

Projects

Environmental & Social Review Summary

Project Number

39743

Company Name

KM TERMINAL AND LOGISTICS LIMITED

Date ESRS Disclosed

Mar 26, 2018

Country

Myanmar

Region

East Asia and the Pacific

Last Updated Date

Oct 18, 2025

Environmental Category

B - Limited

Status

Completed

Previous Events

Approved : May 11, 2018
Signed : May 28, 2018
Invested : Jun 26, 2018

Sector

Other Support Activities for Transportation (Grain Terminals, Cargo Terminals, Airport Operations)

Industry

Infrastructure

Department

Regional Industry - INF Asia & Pac

Project Description

Kerry Logistics Network (“KLN”) is one of Asia’s leading third-party logistics company based in Hong Kong. KLN Singapore, a wholly owned subsidiary of KLN, is developing two greenfield dry ports at Mandalay and Yangon through its subsidiary company KM Terminals and Logistics Limited Myanmar (“KMTL” or the “company”). IFC is considering providing an A loan of US$ 15 million to KMTL to support its dry port development program (“Project”). However, IFC’s funds will be used to part finance construction of the Yangon dry port (the “Dry Port” ).

 

The Dry Port is located in Ywar Thar Gyi, Dagon (East) Township, Yangon Region. The Dry Port is being developed on a 40 acre land leased to KMTL by Myanmar Railways (“MR”). The dry port project site is in the Ywar Thar Gyi railway station yard, immediately adjoining the Yangon-Mandalay railway line which forms its East boundary. A second dry port being developed by another sponsor, also on a 40 acre land, immediately adjoins the Dry Port on its south side. There are agricultural fields West of the Dry Port site. A 1.1 km access road that will serve both the proposed dry ports and other existing industrial facilities is being constructed by KMTL. In 2019, Yangon Dry Port is expected to handle 54,000 TEU container cargo with a design capacity to handle upto 177,000 TEUs. The Dry Port is under construction, an EPC contractor mobilized on April 2017, a Project Management Consultant (PMC) was hired by the company, and the Dry Port is expected to be commissioned by October 2018.

 

The dry port facility will have: paved container handling and storage yard (29,000 m2); reefer handling and storage yard (900 m2); container stripping and stuffing areas and break bulk cargo handling and storage area (3,000 m2); container X Ray facility (2400 m2); railway siding and marshalling yard (10,500 m2); operation space of vehicles and machinery (16,000 m2);  parking space for cargo vehicles and machinery (20,000 m2); quarantine, warehousing space for freight and containers (Export, Import, storage); workshop for light repair of containers; electronic weighbridge; electric distribution; administration complex with offices for Dry Port employees and shipping line delegates; office building for customs; facility housing the IT infrastructure for Dry Port operation; security gate and guard house; boundary wall; rest areas; and bank branch.

 

The operational phase for the Dry Port would primarily involve: (i) transportation activities including container receipt and dispatch on rail train and by road transport vehicles/trucks. The road transport will be undertaken by third party transportation agencies including a KMTL subsidiary; (ii) storage of containers; (iii) Dry Port and container cleaning activities; (iv) maintenance of containers and equipment; and (v) other activities such as office/administrative functions. Equipment that will be deployed in the dry port includes yard tractors, yard chassis/trailer, 2 nos. Rubber Tyre Gantry Cranes (RTGCs), 3nos. of Reach Stackers, 8 nos. of fork lift, 24 nos. of reefers, 10 nos. of road transport vehicles and 750KVA diesel generators (DG) for backup power. It is expected that at full capacity 3 full rake trains will arrive and depart daily and 250 trucks/road transport vehicles will arrive/depart daily.]

                                                

Overview of IFC's Scope of Review

Since IFC’s funds will be used for Yangon dry port development, IFC’s review consisted of appraising technical, environmental and social information related to the Dry Port submitted by KMTL including: Initial Environmental Examination for the Yangon Dry Port dated December 2016;  Land Acquisition and Resettlement Review Report dated February 2018; KMTL Human Resource Policy Handbook; KMTL corporate social responsibility (CSR) plan; KMTL safety procedures related to emergencies, operational control, lifting tools, railways and personal protective equipment; security personnel procedure; sample muster and wage registers for contract workers; sample Dry Port performance, review, audit and monitoring reports.

 

The review included a visit to the Yangon Dry Port site in January 2018 and included a discussion with the company’s Project Director, Project Manager and technical management professionals, project management company’s professionals at site, the EPC contractor’s Project Manager, EPC contractor’s HSE staff, and consultation with a sample of informal settlers who have been resettled.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan