PROJECT

Projects

Environmental & Social Review Summary

Project Number

39652

Company Name

CENTRAIS ELETRICAS DE SERGIPE S.A.

Date ESRS Disclosed

Oct 6, 2017

Country

Brazil

Region

Latin America and the Caribbean

Last Updated Date

Mar 1, 2024

Environmental Category

A - Significant

Status

Completed

Previous Events

Approved : Dec 14, 2017
Signed : Apr 12, 2018
Invested : Jun 21, 2018

Sector

Gas - Thermal Power Generation

Industry

Infrastructure

Department

Regional Industry INF LAC & EUR

Project Description

CELSE Centrais Elétricas de Sergipe S.A. (“CELSE” or the “Sponsor”) is developing the Power Plant Port of Sergipe I (“Project”), a greenfield gas-fired combined cycle thermal power plant and associated infrastructure. CELSE was created in 2015 by EBRASIL- Eletricidade do Brasil and Golar Power (a joint-venture between Golar LNG and Stonepeak Infrastructure Partners). 

The project consists of a 1,500 MW combined-cycle power plant using three GE 7HA.02 gas turbines (GTs) with corresponding Heat Recovery Steam Generators (HRSG) and one steam turbine (ST). It will be connected to the grid via a 34.2 km double circuit 500-kV transmission line and air-insulated connection bay linking to an existing substation with potential to receive up to 3,000 MW.  The project further includes a fully dedicated chartered floating storage and regasification unit (FSRU) with a storage capacity of 170,000 m3 and a liquefied natural gas (LNG) regasification capacity of up to 14 million m3/day with a Submerged Soft Yoke (SSY) mooring structure. The FRSU will be located 6.5 km offshore and will connect to the power plant via an 18-inch diameter offshore and onshore gas pipeline to transfer the regasified LNG (RLNG) from the FSRU to the combined-cycle power plant. Seawater cooling towers will be used for the condenser cooling. The water intake and cooling water discharge are located offshore, and are connected to the power plant with pipelines that follow routing along to the RLNG pipeline with a seawater pumping station located on-shore.

The power plant will be constructed on a 511,622 m² site located in the Municipality of Barra dos Coqueiros, approximately 20 km from Aracaju, the capital of Sergipe State, in northeastern Brazil. 

The project is potentially the first of three gas-fired power plants to be developed by CELSE’s Sponsors at the site. As per initial studies, CELSE’s Sponsors intends to pursue development of two additional gas-fired plants within the same site area, for a total of approximately 3,000 MW of generating capacity although timing of future developments has yet to be determined.

The FSRU, named “Golar Nanook”, is a new FSRU with a regasification capacity of 14 million m3/ day, currently under construction at the Samsung Heavy Industries (SHI) shipyard. LNG delivery to the FSRU will be through Ship-to-Ship (STS) process. The FSRU is being chartered to the project by Golar Power, one of the Project Sponsors. The submerged pipeline will lie on the seabed except for the nearshore portion which will be buried. Once past the shoreline the pipeline continues for a distance of 1.5 km and terminates at a gate which has three branches (Porto de Sergipe I and two future facilities).

General Electric (GE) is under a turnkey Engineer Procure Construct (EPC) contract to provide the power plant, the 34.2-km transmission line, the substation expansion, and the sea-water intake/discharge infrastructure for the power plant’s cooling requirements. The installation of the SSY and the construction of the gas pipeline will be contracted under separate EPC contract with Sapura Energy. For the operational phase of the project, CELSE has selected GE as the operations and maintenance (O&M) contractor for the power plant and GOLAR LNG as the O&M operator for the FRSU.

The transmission line will have a 70-meter wide right-of-way (ROW) and an approximate total of 60 towers. The TL will cross the municipalities of Barra dos Coqueiros (site of the power plant), Santo Amaro das Brotas, Laranjeiras and Nossa Senhora do Socorro (site of the CHESF’s Jardim Substation and the proposed CELSE’ bay).

The site of the power plant had previously been cleared and prepared to serve as an industrial site and is located near the State Road SE-100 and 1.2 km from Praia do Jatoba, on the Atlantic Ocean, near the Community of Praia do Jatoba. The power plant site is separated from the Community of Praia do Jatoba by the Wind Farm Barra dos Coqueiros. An existing marine terminal “Terminal Maritimo Inacio Barbosa (TMIB)” is located adjacent, and south/southwest of the power plant site. The TMIB will be used to receive large pieces of equipment for the project. State road SE-100 is located immediately to the west of the power plant site and provides a connection to local communities including the City of Aracaju. 

The project will operate as a backup base load power plant and is expected to dispatch to the national grid between 30-50% of the time, as required by the Electric System National Operator (ONS – Operador Nacional do Sistema Eletrico). The power plant is currently under construction with start of operation scheduled for January, 2020. The FSRU construction is expected to be completed by the second semester of 2018 and will arrive at the site during the last quarter of 2018. Total project cost is estimated at US$ 1.8 billion, and IFC proposed investment in the project is up to US$ 200 million A loan. Site preparation started in December 2016.

Overview of IFC's Scope of Review

The IFC scope of review during the CELSE’s appraisal included review of three ESIAs (TL, power plant and FRSU/offshore structures), field studies, mathematical models (e.g., noise, air dispersion, thermal discharge, quantitative risk analyses [QRA]), occupational health and safety plans and management plans for the construction and operational phases of the Project. Due to the complexity and footprint of the project, IFC’s E&S specialists conducted a 5-day site visit (May 7-12, 2017), which included the following activities: 1) meetings and interviews with CELSE’s directors, managers, E&S personnel and consultants (environmental, social, and engineering experts), EPC Contractor’s project directors and managers; 2) meetings with environmental regulatory agencies (ADEMA and IBAMA); 3) meeting at the Town Hall of Barra dos Coqueiros; 4) meetings with representatives from the Quilombola Community Pontal da Barra; Cajueiro; Praia do Jatoba; the fisherman association of Pirambu (Colônia Z15); 5) interviews with stakeholders who had their houses acquired by CELSE in Praia do Jatoba; 6) field visit to the location of the power plant, transmission line and surrounding areas; and 7) conference calls and meetings with CELSE following the site visit.

E & S Project Categorization and Applicable Standard

Environmental and Social Mitigation Measures

Stakeholder Engagement

Broad Community Support

Environmental & Social Action Plan

Client Documentation

File Name Actions
Integrated_ESIA_Exec_Summary_10.1.3.4.1_Volume_I_Introdutorios-Rev.03.pdf
Integrated_ESIA_Exec_Summary_Anexo_I_Ruido.pdf
Integrated_ESIA_Exec_Summary_Anexo_II. Atm.pdf
Integrated_ESIA_Exec_Summary_Apêndice_A-Avaliação_de_Impacto_Cumulativo.pdf
Integrated_ESIA_Exec_Summary_Executive_Summary.pdf
Integrated_ESIA_Exec_Summary_Resumo_Executivo.pdf
Integrated_ESIA_Exec_Summary_VOLII_Cap7.1_DiagFISICO.pdf
Integrated_ESIA_Exec_Summary_VOLII-ANEXO.pdf
Integrated_ESIA_Exec_Summary_VOLIII_Cap7.2_DiagBIOTICO.pdf
Integrated_ESIA_Exec_Summary_VOLIII-ANEXOCapitulo7.2.pdf
Integrated_ESIA_Exec_Summary_VOLIV_Cap7.3_DiagSOCIAL.pdf
Integrated_ESIA_Exec_Summary_VOLIV-ANEXOS.pdf
Integrated_ESIA_Exec_Summary_VOLV_Cap8a13.pdf
Integrated_ESIA_Exec_Summary_VOLV-ANEXOCapitulo 8.pdf
Integrated_ESIA_Executive_Summary_PBAq_rev2.pdf
Integrated_ESIA_Executive_Summary_PCAO_rev2.pdf
Integrated_ESIA_Executive_Summary_PCFa_rev2.pdf
Integrated_ESIA_Executive_Summary_PCFl_rev2.pdf
Integrated_ESIA_Executive_Summary_PCME_rev2.pdf
Integrated_ESIA_Executive_Summary_PCMO_rev2.pdf
Integrated_ESIA_Executive_Summary_PCPC_rev2.pdf
Integrated_ESIA_Executive_Summary_PCPE_rev2.pdf
Integrated_ESIA_Executive_Summary_PCRI_rev2.pdf
Integrated_ESIA_Executive_Summary_PCS_rev2.pdf
Integrated_ESIA_Executive_Summary_PDF_rev02.pdf
Integrated_ESIA_Executive_Summary_PEA-PEAT_rev2.pdf
Integrated_ESIA_Executive_Summary_PGA_Anexo_B1-Digital.xlsx
Integrated_ESIA_Executive_Summary_PGA_Anexo_B2-Digital.xlsx
Integrated_ESIA_Executive_Summary_PGA_Anexo_C2-DIGITAL.xlsx
Integrated_ESIA_Executive_Summary_PGA_rev2.pdf
Integrated_ESIA_Executive_Summary_PGRS_rev2.pdf
Integrated_ESIA_Executive_Summary_PMAP_rev2.pdf
Integrated_ESIA_Executive_Summary_PMEA_rev2.pdf
Integrated_ESIA_Executive_Summary_PMH_rev2.pdf
Integrated_ESIA_Executive_Summary_PMIS_rev2.pdf
Integrated_ESIA_Executive_Summary_PMRV_rev2.pdf
Integrated_ESIA_Executive_Summary_PPC_rev2.pdf
Integrated_ESIA_Executive_Summary_PRAD_rev2.pdf
Integrated_ESIA_Executive_Summary_PRRMS_rev2.pdf
GN_UTE_ESIA_Anexo4_Alternativa_Locacional_EIA_UTE_GN.SE.005-17.pdf
GN_UTE_ESIA_EIA_UTE_rev00_v06.pdf
CH2M_RAS_TL_2017_Anexo9.3-1_Mapas_de_Intervencao.pdf
CH2M_RAS_TL_2017_AnexoA-Flora.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-2-Levantamento_de_Arvores_Isoladas.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-3-Localizacao_das_Parcelas_Amostradas_de_Flora.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-4-Relatorio_fotografico_das_Parcelas_Amostrais_de_Flora.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-5-Dados_Brutos_Floresta_Estacional_Semidecidual.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-6-Dados _Brutos_Manguezal.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-7-Dados_Brutos_Restinga.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-9-Dados_Bruto_Herpeto_Fauna.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-10-Dados_Bruto_Avifauna.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_ANEXO7.2-11-Dados_brutos_masto.docx
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_Mapa_de_Fragilidade_Ambiental_da_AID_da_LT.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese1.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese2.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese3.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese4.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese5.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese6.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese7.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese8.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese9.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_MAPA_Sintese10.pdf
CH2M_RAS_TL_2017_ANEXOS-BIOTICO_TEC_ACF-0001_AutCap.pdf
CH2M_RAS_TL_2017_Anexos-SOCIOECONOMICO_ANEXO7.3-1-Uso_Solo_LT.pdf
CH2M_RAS_TL_2017_Anexos-SOCIOECONOMICO_ANEXO7.3-2-Mapa_de_localizacao_de_acessos_da_LT.pdf
CH2M_RAS_TL_2017_Anexos-SOCIOECONOMICO_ANEXO7.3-3-Propriedades_Interceptadas_pela_LT.pdf
CH2M_RAS_TL_2017_Cap1a6-Intros_LT_revTR.pdf
CH2M_RAS_TL_2017_Cap8a15_LT_revTR.pdf
CH2M_RAS_TL_2017_DiagBIOTICO_LT_3.pdf
CH2M_RAS_TL_2017_DiagFISICO_LT_7.pdf
CH2M_RAS_TL_2017_DiagSOCIO_LT_revTR.pdf