38506
METROPOLITAN MUNICIPALITY OF ANTALYA
Aug 9, 2017
Turkiye
Central Asia and Turkiye
May 18, 2018
B - Limited
Active
Approved : Oct 18, 2017
Signed : Nov 17, 2017
Invested : May 16, 2018
Municipal Finance - Transport and Roads [Project only]
Infrastructure
Regional Industry INF MCT
The proposed investment is to provide an A loan of up to EUR 80 million and a Managed Co-Lending Portfolio Program (MCPP) loan up to EUR 60 million to Metropolitan Municipality of Antalya ("MMA"), to finance the construction of a new 18.2 km tramway line with 29 stations and purchasing 20 tram vehicles (or tram cars); which altogether constitutes Phase-3A tramway line project (“the project”).
The project sponsor is MMA, serving a population of nearly 2.3 million inhabitants of Antalya, the 5 th largest metropolitan municipality in Turkey. The project will be implemented by MMA’s transportation planning and railway systems department and operated by Antalya Ulasim A.S. (“Antalya Ulasim”), the municipal enterprise responsible for operation of MMA’s urban public transportation network.
Antalya has two tramway lines which are already operational: the 11-km Fatih-Meydan line (Phase-1) and the 19-km Meydan-Expo line extension (Phase-2), which was constructed by the Ministry of Transportation. Phase-3 tramway line implementation has been divided in two phases: i) as indicated above, Phase-3A which covers the construction of a new 18.2 km tramway line (Varsak-Otogar-Muze) with 29 stations and a depot and maintenance facility plus procurement of 20 tram vehicles; and ii) Phase-3B which covers the rehabilitation and conversion from single-track to double-track of 4.2 km nostalgic tramway line (Muze-Zerdalilik) with 10 stations plus procurement of 12 tram vehicles and is planned to start construction in 2019.
The Phase-3 tramway line will connect the city’s northern populated but underprivileged neighborhoods to its center, along the coast on north side of the Antalya Bay, where the main bus station, city museum, state hospital, university, university hospital, judicial court and sports hall are located. The line will be fully integrated with the existing Phase-1 and Phase-2 tramway lines and bus stations. The new tramway will be electrified and will run on dedicated lanes within the central median along arterial roads. The tramway lanes will be constructed on land that belongs to MMA, thus minimizing the need for expropriation.
Phase-3A line construction will only require limited footprint aboveground and will have a short section underground at the main bus station, where the line joins with Phase-1. This will require construction of 1.3 km long tunnel (including a cut-and-cover section). The tunneling method is defined as New Austrian Tunneling Method (NATM) and this will be taken into account for the finalization of the relevant safety and environmental procedures.
The tramway line and stations will require an area of 32.5 ha in total, while the depot and maintenance facility, to be built in the Varsak region in the north of the city center on land owned by the Prime Ministry Under-secretariat of Treasury, will require a total of 6 ha including 1 km of connection line to Phase-3A tram line.
The Phase-3A line is designed to carry about 51,000 commuters per weekday when it will become operational. Construction is expected to start in December 2017, will involve a turnkey contract with an Engineering, Procurement, and Construction (EPC) contractor and will be completed in the first half of 2019; construction is estimated to last 18 months.
IFC and Architecture 2030 Collaborate on Global Target of Zero Net Carbon Buildings
IFC’s review of the project consisted of appraising the following technical, environmental, and social information provided by MMA:
- Antalya Phase 3 Rail System Lines Feasibility Report, Bogazici Proje Engineering Planning & Construction Ltd., dated May 2017.
- Project Description File (Preliminary Environmental Impact Assessment), revised by Cinar Engineering & Consultancy A.S., dated May 2017.
Three appraisal visits to the project sites and its surrounding areas were conducted on October 4-6 and November 2-3, 2016 and on May 07, 2017. Visits included the tram lines in operation (Phase 1 and 2), the existing depot and maintenance facility, the Phase 3 tram line route, and the location of new depot and maintenance facility. Meetings were held with the chief financial officer, human resources department, managers and representatives of Transportation Planning and Railway Systems Department of MMA. Meetings were also held with the consultants responsible for engineering feasibility and design (Yuksel Proje International A.S. and Bogazici Proje Engineering Planning & Construction Ltd.) for the Phase-3 project. Representatives of Antalya Ulasim, including staff that provide oversight for environmental, social, health and safety (E&S) performance of the two operational lines, provided information on current E&S practices. As the project design was changed as per the recommendations of General Directorate of Infrastructure Investments of Ministry of Transport, Maritime Affairs and Communication, the appraisal visit by IFC on May 2017 focused on reviewing changes in terms of E&S risk profile, associated with the new project design and features.